| Day | Regulation (10 CFR) | Action |
|---|---|---|
| 0 | 2.101(f)(8), 2.105(a)(5) | Federal Register Notice of Hearing. |
| 30 | 2.309(b)(2) | Petition to intervene/request for hearing, w/contentions. |
| 30 | 2.309(b)(2) | Petition for status as interested government participant. |
| 55 | 2.315(c) | Answers to intervention & interested government participant Petitions. |
| 62 | 2.309(h)(1) | Petitioner's response to answers. |
| 70 | 2.1021 | First Prehearing conference. |
| 100 | 2.309(h)(2) | First Prehearing Conference Order identifying participants in proceeding, admitted contentions, and setting discovery and other schedules. |
| 110 | 2.1021 | Appeals from First Prehearing Conference Order. |
| 120 | Briefs in opposition to appeals. | |
| 150 | 2.1021, 2.329 | Commission ruling on appeals for First Prehearing Conference Order. |
| 548 | NRC Staff issues SER. | |
| 578 | 2.1022 | Second Prehearing Conference. |
| 608 | 2.1021, 2.1022 | Discovery complete; Second Prehearing Conference Order finalizes issues for hearing and sets schedule for prefiled testimony and hearing. |
| 618 | 2.1015(b) | Appeals from Second Prehearing Conference Order. |
| 628 | 2.1015(b), c.f. 2.710(a) | Briefs in opposition to appeals; last date for filing motions for summary disposition. |
| 648 | c.f. 2.710(a) | Last date for responses to summary disposition motions. |
| 658 | 2.710(a) | Commission ruling on appeals from Second Prehearing Conference Order; last date for party opposing summary disposition motion to file response to new facts and arguments in any response supporting summary disposition motion. |
| 698 | 2.1015(b) | Decision on summary disposition motions (may be determination to dismiss or to hold in abeyance). |
| 720 | c.f. 2.710(a) | Evidentiary hearing begins. |
| 810 | Evidentiary hearing ends. | |
| 840 | 2.712(a)(1) | Applicant's proposed findings. |
| 850 | 2.712(a)(2) | Other parties' proposed findings. |
| 855 | 2.712(a)(3) | Applicant's reply to other parties' proposed findings. |
| 955 | 2.713 | Initial decision. |
| 965 | 2.342(a), 2.345(a), 2.1015(c)(1) | Stay motion. Petition for reconsideration, notice of appeal. |
| 975 | 2.342(d), 2.345(b) | Other parties' responses to stay motion and Petitions for reconsideration. |
| 985 | Commission ruling on stay motion. | |
| 995 | 2.1015(c)(2) | Appellant's briefs. |
| 1015 | 2.1015(c)(3) | Appellee's briefs. |
| 1055 | 2.1023 Supp. Info | Completion of NMSS and Commission supervisory review; issuance of construction authorization; NWPA 3-year period tolled. |
| 1125 | Commission decision. |
Title 10 published on 2012-01-01
The following are only the Rules published in the Federal Register after the published date of Title 10.
For a complete list of all Rules, Proposed Rules, and Notices view the Rulemaking tab.
GPO FDSys XML | Text type regulations.gov FR Doc. 2012-21207 RIN 3150-AI77 NRC-2010-0012 NUCLEAR REGULATORY COMMISSION Final rule and regulatory guide, issuance. The effective date is September 27, 2012. 10 CFR Parts 2 and 52 The U.S. Nuclear Regulatory Commission (NRC or the Commission) is amending its regulations related to verification of nuclear power plant construction activities through inspections, tests, analyses, and acceptance criteria (ITAAC) under a combined license, and issuing a revision to Regulatory Guide (RG) 1.215, “Guidance for ITAAC Closure Under 10 CFR [Title 10 of the Code of Federal Regulations ] Part 52.” The final rule contains new provisions that apply after a licensee has completed an ITAAC and submitted an ITAAC closure notification. The new provisions require licensees to report new information materially altering the basis for determining that inspections, tests, or analyses were performed as required, or that acceptance criteria are met, and to notify the NRC of the completion of all ITAAC activities. In addition, the NRC is including editorial corrections to existing language in the NRC's regulations to make that language consistent with language in the Atomic Energy Act of 1954, as amended (AEA). Regulatory Guide 1.215 describes a method that the staff of the NRC considers acceptable for use in satisfying the requirements for documenting the completion of ITAAC.
GPO FDSys XML | Text type regulations.gov FR Doc. 2012-18278 RIN 3150-AI43 NRC-2008-0415 NUCLEAR REGULATORY COMMISSION Final rule. The effective date is September 4, 2012. 10 CFR Parts 2, 12, 51, 54, and 61 The U.S. Nuclear Regulatory Commission (NRC or the Commission) is amending its adjudicatory rules of practice. This rule makes changes to the NRC's adjudicatory process that the NRC believes will promote fairness, efficiency, and openness in NRC adjudicatory proceedings. This rule also corrects errors and omissions that have been identified since the major revisions to the NRC's rules of practice in early 2004.
GPO FDSys XML | Text type regulations.gov FR Doc. 2012-16252 RIN 3150-AJ14 NRC-2012-0062 NUCLEAR REGULATORY COMMISSION Direct final rule. The direct final rule will become effective on August 22, 2012, unless significant adverse comments on the amendment are received by August 2, 2012. If the rule is withdrawn as a result of such comments, timely notice of the withdrawal will be published in the Federal Register . Comments received after August 2, 2012 will be considered if it is practical to do so, but the NRC is able to ensure consideration only for comments received on or before this date. 10 CFR Parts 2 and 171 The U.S. Nuclear Regulatory Commission (NRC or the Commission) is amending the size standard that it uses to qualify an NRC licensee as a “small entity” under the Regulatory Flexibility Act of 1980, as amended. The NRC is increasing its receipts-based, small business size standard from $6.5 million to $7 million to conform to the standard set by the Small Business Administration (SBA). This size standard reflects the most commonly used SBA size standard for nonmanufacturing industries. The SBA adjusted this standard on July 18, 2008 (73 FR 41237), to account for inflation.
This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.
This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].
It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.
Title 10 published on 2012-01-01
The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 10 CFR 2 after this date.
GPO FDSys XML | Text type regulations.gov FR Doc. 2013-07960 RIN 3150-AJ24 NRC-2013-0050 NUCLEAR REGULATORY COMMISSION Advance notice of proposed rulemaking. Submit comments by July 5, 2013. Comments received after this date will be considered if it is practical to do so, but the NRC is only able to ensure consideration of comments received on or before this date. 10 CFR Part 2 The U.S. Nuclear Regulatory Commission (NRC) is issuing this Advance Notice of Proposed Rulemaking (ANPR) to begin the process of potentially amending its regulations to change the interlocutory appeals process for certain adjudicatory decisions. The NRC seeks public comment on these potential changes to the interlocutory appeals process.
GPO FDSys XML | Text type regulations.gov FR Doc. 2012-21630 RIN 3150-AJ14 NRC-2012-0062 NUCLEAR REGULATORY COMMISSION Direct final rule; confirmation of effective date. The effective date of August 22, 2012, is confirmed for this direct final rule. 10 CFR Parts 2 and 171 The U.S. Nuclear Regulatory Commission (NRC) is confirming the effective date of August 22, 2012, for the direct final rule that appeared in the Federal Register of July 3, 2012 (77 FR 39385). This direct final rule amended the size standard that the NRC uses to qualify an NRC licensee as a “small entity” under the Regulatory Flexibility Act of 1980, as amended. The NRC is increasing its receipts-based, small business size standard from $6.5 million to $7 million to conform to the standard set by the Small Business Administration (SBA). This document confirms the effective date.
GPO FDSys XML | Text type regulations.gov FR Doc. 2012-21207 RIN 3150-AI77 NRC-2010-0012 NUCLEAR REGULATORY COMMISSION Final rule and regulatory guide, issuance. The effective date is September 27, 2012. 10 CFR Parts 2 and 52 The U.S. Nuclear Regulatory Commission (NRC or the Commission) is amending its regulations related to verification of nuclear power plant construction activities through inspections, tests, analyses, and acceptance criteria (ITAAC) under a combined license, and issuing a revision to Regulatory Guide (RG) 1.215, “Guidance for ITAAC Closure Under 10 CFR [Title 10 of the Code of Federal Regulations ] Part 52.” The final rule contains new provisions that apply after a licensee has completed an ITAAC and submitted an ITAAC closure notification. The new provisions require licensees to report new information materially altering the basis for determining that inspections, tests, or analyses were performed as required, or that acceptance criteria are met, and to notify the NRC of the completion of all ITAAC activities. In addition, the NRC is including editorial corrections to existing language in the NRC's regulations to make that language consistent with language in the Atomic Energy Act of 1954, as amended (AEA). Regulatory Guide 1.215 describes a method that the staff of the NRC considers acceptable for use in satisfying the requirements for documenting the completion of ITAAC.
GPO FDSys XML | Text type regulations.gov FR Doc. 2012-18278 RIN 3150-AI43 NRC-2008-0415 NUCLEAR REGULATORY COMMISSION Final rule. The effective date is September 4, 2012. 10 CFR Parts 2, 12, 51, 54, and 61 The U.S. Nuclear Regulatory Commission (NRC or the Commission) is amending its adjudicatory rules of practice. This rule makes changes to the NRC's adjudicatory process that the NRC believes will promote fairness, efficiency, and openness in NRC adjudicatory proceedings. This rule also corrects errors and omissions that have been identified since the major revisions to the NRC's rules of practice in early 2004.
GPO FDSys XML | Text type regulations.gov FR Doc. 2012-16252 RIN 3150-AJ14 NRC-2012-0062 NUCLEAR REGULATORY COMMISSION Direct final rule. The direct final rule will become effective on August 22, 2012, unless significant adverse comments on the amendment are received by August 2, 2012. If the rule is withdrawn as a result of such comments, timely notice of the withdrawal will be published in the Federal Register . Comments received after August 2, 2012 will be considered if it is practical to do so, but the NRC is able to ensure consideration only for comments received on or before this date. 10 CFR Parts 2 and 171 The U.S. Nuclear Regulatory Commission (NRC or the Commission) is amending the size standard that it uses to qualify an NRC licensee as a “small entity” under the Regulatory Flexibility Act of 1980, as amended. The NRC is increasing its receipts-based, small business size standard from $6.5 million to $7 million to conform to the standard set by the Small Business Administration (SBA). This size standard reflects the most commonly used SBA size standard for nonmanufacturing industries. The SBA adjusted this standard on July 18, 2008 (73 FR 41237), to account for inflation.
GPO FDSys XML | Text type regulations.gov FR Doc. 2012-16258 RIN 3150-AJ14 NRC-2012-0062 NUCLEAR REGULATORY COMMISSION Proposed rule. Submit comments by August 2, 2012. Comments received after this date will be considered if it is practical to do so, but the NRC is able to assure consideration only for comments received on or before this date. 10 CFR Parts 2 and 171 The U.S. Nuclear Regulatory Commission (NRC or the Commission) is proposing to amend the size standard that it uses to qualify an NRC licensee as a “small entity” under the Regulatory Flexibility Act of 1980, as amended. The NRC is proposing to increase its receipts-based, small business size standard from $6.5 million to $7 million to conform to the standard set by the Small Business Administration (SBA). This size standard reflects the most commonly used SBA size standard for nonmanufacturing industries. The SBA adjusted this standard on July 18, 2008 (73 FR 41237), to account for inflation.