10 CFR 205.329 - Environmental requirements for Presidential Permits

prev | next
§ 205.329 Environmental requirements for Presidential Permits—Alternative 2.
(a) NEPA Compliance. Except as provided in paragraph (b) and (e) of this section, applicants seeking Presidential Permits will be financially responsible for the expenses of any contractor chosen by ERA to prepare any necessary environmental document arising from ERA's obligation to comply with the National Environmental Policy Act of 1969 (NEPA) in issuing such Presidential Permits:
(1) ERA will determine whether an Environmental Impact Statement (EIS) or an Environmental Assessment (EA) is required within 45 days of receipt of the Presidential Permit application and of the environmental information submitted pursuant to 10 CFR 205.322 (c) and (d). ERA will use these and other sources of information as the basis for making the environmental determination.
(2) If an EIS is determined to be necessary, ERA will notify the applicant of the fee for completing the EIS within 90 days after the submission of the application and environmental information. The fee shall be based on the expenses estimated to be incurred by DOE in contracting to prepare the EIS (i.e., the estimated fee charges to ERA by the contractor). DOE employee salaries and other fixed costs, as set forth in OMB Circular A-25, shall not be included in the applicant's fee. Fee payment shall be by check, draft, or money order payable to the Treasurer of the United States, and shall be submitted to ERA. Upon submission of fifty percent of the environmental fee, ERA will provide to the applicant a tentative schedule for completion of the EIS.
(3) If an EA is determined to be necessary, the applicant may be permitted to prepare an environmental assessment pursuant to 40 CFR 1506.5(b) for review and adoption by ERA, or the applicant may choose to have ERA prepare the EA pursuant to the fee procedures set forth above.
(4) The NEPA process must be completed and approved before ERA will issue a Presidential Permit.
(b) Financial Hardship. Whenever ERA determines that a project is no longer economically feasible, or that a substantial financial burden would be imposed by the applicant bearing all of the costs of the NEPA studies, ERA may waive the requirement set forth in paragraphs (a) and (b) of this section and perform the necessary environmental review, completely or in part, with its own resources.
(c) Discussions Prior to Filing. Prior to the preparation of any Presidential Permit application and environmental assessment, a potential applicant is encouraged to contact ERA and each affected State public utility regulatory agency to discuss the scope of the proposed project and the potential for joint State and Federal environmental review.
(d) Fee Payment. The applicant shall make fee payment for completing the EIS to ERA in the following manner:
(1) 50 percent of the total amount due to be paid within 30 days of receipt of the fee information from DOE;
(2) 25 percent to be paid upon publication of the draft EIS; and
(3) 25 percent to be paid upon publication of the final EIS.
If costs are less than the amount collected, ERA will refund to the applicant the excess fee collected. If costs exceed the initial fee, ERA will fund the balance, unless the increase in costs is caused by actions or inactions of the applicant, such as the applicant's failure to submit necessary environmental information in a timely fashion. If the application is withdrawn at any stage prior to issuance of the final EIS, the fee will be adjusted to reflect the costs actually incurred; payment shall be made by the applicant within 30 days of above referenced events.
(e) Federal Exemption. Upon a showing by the applicant that it is engaged in the transaction of official business of the Federal Government in filing an application pursuant to 10 CFR 205.320 et seq., it will be exempt from the requirements of this section.
[48 FR 33820, July 25, 1983]

Title 10 published on 2014-01-01

no entries appear in the Federal Register after this date.

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code
U.S. Code: Title 16 - CONSERVATION

§ 791 - Repealed. Aug. 26, 1935, ch. 687, title II,

§ 791a - Short title

§ 792 - Federal Power Commission; creation; number; appointment; term; qualifications; vacancies; quorum; chairman; salary; place of holding sessions

§ 793 - Appointment of officers and employees of Commission; duties, and salaries; detail of officers and employees from other departments; expenditures authorized

§ 793a - Repealed.

§ 794, 795 - Omitted

§ 796 - Definitions

§ 797 - General powers of Commission

§ 797a - Congressional authorization for permits, licenses, leases, or authorizations for dams, conduits, reservoirs, etc., within national parks or monuments

§ 797b - Duty to keep Congress fully and currently informed

§ 797c - Dams in National Park System units

§ 797d - Third party contracting by FERC

§ 798 - Purpose and scope of preliminary permits; transfer and cancellation

§ 799 - License; duration, conditions, revocation, alteration, or surrender

§ 800 - Issuance of preliminary permits or licenses

§ 801 - Transfer of license; obligations of transferee

§ 802 - Information to accompany application for license; landowner notification

§ 803 - Conditions of license generally

§ 804 - Project works affecting navigable waters; requirements insertable in license

§ 805 - Participation by Government in costs of locks, etc.

§ 806 - Time limit for construction of project works; extension of time; termination or revocation of licenses for delay

§ 807 - Right of Government to take over project works

§ 808 - New licenses and renewals

§ 809 - Temporary use by Government of project works for national safety; compensation for use

§ 810 - Disposition of charges arising from licenses

§ 811 - Operation of navigation facilities; rules and regulations; penalties

§ 812 - Public-service licensee; regulations by State or by commission as to service, rates, charges, etc.

§ 813 - Power entering into interstate commerce; regulation of rates, charges, etc.

§ 814 - Exercise by licensee of power of eminent domain

§ 815 - Contract to furnish power extending beyond period of license; obligations of new licensee

§ 816 - Preservation of rights vested prior to June 10, 1920

§ 817 - Projects not affecting navigable waters; necessity for Federal license, permit or right-of-way; unauthorized activities

§ 818 - Public lands included in project; reservation of lands from entry

§ 819 - Repealed. Aug. 26, 1935, ch. 687, title II,

§ 820 - Proceedings for revocation of license or to prevent violations of license

§ 821 - State laws and water rights unaffected

§ 822 - Reservation of right to alter or repeal chapter

§ 823 - Repeal of inconsistent laws

§ 823a - Conduit hydroelectric facilities

§ 823b - Enforcement

§ 823c - Alaska State jurisdiction over small hydroelectric projects

§ 823d - Alternative conditions and prescriptions

U.S. Code: Title 42 - THE PUBLIC HEALTH AND WELFARE
Statutes at Large
Public Laws
Presidential Documents

Executive Order ... 10485

Executive Order ... 11790

Executive Order ... 12009

Executive Order ... 12038