§ 50.34a Design objectives for equipment to control releases of radioactive material in effluents—nuclear power reactors.
(a) An application for a construction permit shall include a description of the preliminary design of equipment to be installed to maintain control over radioactive materials in gaseous and liquid effluents produced during normal reactor operations, including expected operational occurrences. In the case of an application filed on or after January 2, 1971, the application shall also identify the design objectives, and the means to be employed, for keeping levels of radioactive material in effluents to unrestricted areas as low as is reasonably achievable. The term “as low as is reasonably achievable” as used in this part means as low as is reasonably achievable taking into account the state of technology, and the economics of improvements in relation to benefits to the public health and safety and other societal and socioeconomic considerations, and in relation to the use of atomic energy in the public interest. The guides set out in appendix I to this part provide numerical guidance on design objectives for light-water-cooled nuclear power reactors to meet the requirements that radioactive material in effluents released to unrestricted areas be kept as low as is reasonably achievable. These numerical guides for design objectives and limiting conditions for operation are not to be construed as radiation protection standards.
(b) Each application for a construction permit shall include:
(1) A description of the preliminary design of equipment to be installed under paragraph (a) of this section;
(2) An estimate of:
(i) The quantity of each of the principal radionuclides expected to be released annually to unrestricted areas in liquid effluents produced during normal reactor operations; and
(ii) The quantity of each of the principal radionuclides of the gases, halides, and particulates expected to be released annually to unrestricted areas in gaseous effluents produced during normal reactor operations.
(3) A general description of the provisions for packaging, storage, and shipment offsite of solid waste containing radioactive materials resulting from treatment of gaseous and liquid effluents and from other sources.
(c) Each application for an operating license shall include:
(1) A description of the equipment and procedures for the control of gaseous and liquid effluents and for the maintenance and use of equipment installed in radioactive waste systems, under paragraph (a) of this section; and
(2) A revised estimate of the information required in paragraph (b)(2) of this section if the expected releases and exposures differ significantly from the estimates submitted in the application for a construction permit.
(d) Each application for a combined license under part 52 of this chapter shall include:
(1) A description of the equipment and procedures for the control of gaseous and liquid effluents and for the maintenance and use of equipment installed in radioactive waste systems, under paragraph (a) of this section; and
(2) The information required in paragraph (b)(2) of this section.
(e) Each application for a design approval, a design certification, or a manufacturing license under part 52 of this chapter shall include:
(1) A description of the equipment for the control of gaseous and liquid effluents and for the maintenance and use of equipment installed in radioactive waste systems, under paragraph (a) of this section; and
(2) The information required in paragraph (b)(2) of this section.
[72 FR 49492, Aug. 28, 2007]

Title 10 published on 2014-01-01

The following are only the Rules published in the Federal Register after the published date of Title 10.

For a complete list of all Rules, Proposed Rules, and Notices view the Rulemaking tab.

  • 2014-10-17; vol. 79 # 201 - Friday, October 17, 2014
    1. 79 FR 62329 - Definition of a Utilization Facility
      GPO FDSys XML | Text
      NUCLEAR REGULATORY COMMISSION, 10 CFR Part 50
      Direct final rule.
      This final rule is effective December 31, 2014, unless a significant adverse comment is received by November 17, 2014. If the rule is withdrawn as a result of such comments, timely notice of the withdrawal will be published in the Federal Register . Comments received after this date will be considered if it is practical to do so, but the NRC is able to ensure consideration only for comments received on or before this date.

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code
Statutes at Large

Title 10 published on 2014-01-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 10 CFR 50 after this date.

  • 2014-10-17; vol. 79 # 201 - Friday, October 17, 2014
    1. 79 FR 62329 - Definition of a Utilization Facility
      GPO FDSys XML | Text
      NUCLEAR REGULATORY COMMISSION, 10 CFR Part 50
      Direct final rule.
      This final rule is effective December 31, 2014, unless a significant adverse comment is received by November 17, 2014. If the rule is withdrawn as a result of such comments, timely notice of the withdrawal will be published in the Federal Register . Comments received after this date will be considered if it is practical to do so, but the NRC is able to ensure consideration only for comments received on or before this date.