§ 50.40 Common standards.
In determining that a construction permit or operating license in this part, or early site permit, combined license, or manufacturing license in part 52 of this chapter will be issued to an applicant, the Commission will be guided by the following considerations:
(a) Except for an early site permit or manufacturing license, the processes to be performed, the operating procedures, the facility and equipment, the use of the facility, and other technical specifications, or the proposals, in regard to any of the foregoing collectively provide reasonable assurance that the applicant will comply with the regulations in this chapter, including the regulations in part 20 of this chapter, and that the health and safety of the public will not be endangered.
(b) The applicant for a construction permit, operating license, combined license, or manufacturing license is technically and financially qualified to engage in the proposed activities in accordance with the regulations in this chapter. However, no consideration of financial qualification is necessary for an electric utility applicant for an operating license for a utilization facility of the type described in § 50.21(b) or § 50.22 or for an applicant for a manufacturing license.
(c) The issuance of a construction permit, operating license, early site permit, combined license, or manufacturing license to the applicant will not, in the opinion of the Commission, be inimical to the common defense and security or to the health and safety of the public.
(d) Any applicable requirements of subpart A of 10 CFR part 51 have been satisfied.
[72 FR 49493, Aug. 28, 2007]

Title 10 published on 2014-01-01

The following are only the Rules published in the Federal Register after the published date of Title 10.

For a complete list of all Rules, Proposed Rules, and Notices view the Rulemaking tab.

  • 2014-10-17; vol. 79 # 201 - Friday, October 17, 2014
    1. 79 FR 62329 - Definition of a Utilization Facility
      GPO FDSys XML | Text
      NUCLEAR REGULATORY COMMISSION, 10 CFR Part 50
      Direct final rule.
      This final rule is effective December 31, 2014, unless a significant adverse comment is received by November 17, 2014. If the rule is withdrawn as a result of such comments, timely notice of the withdrawal will be published in the Federal Register . Comments received after this date will be considered if it is practical to do so, but the NRC is able to ensure consideration only for comments received on or before this date.

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code
Statutes at Large

Title 10 published on 2014-01-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 10 CFR 50 after this date.

  • 2014-10-17; vol. 79 # 201 - Friday, October 17, 2014
    1. 79 FR 62329 - Definition of a Utilization Facility
      GPO FDSys XML | Text
      NUCLEAR REGULATORY COMMISSION, 10 CFR Part 50
      Direct final rule.
      This final rule is effective December 31, 2014, unless a significant adverse comment is received by November 17, 2014. If the rule is withdrawn as a result of such comments, timely notice of the withdrawal will be published in the Federal Register . Comments received after this date will be considered if it is practical to do so, but the NRC is able to ensure consideration only for comments received on or before this date.