§ 50.62
Requirements for reduction of risk from anticipated transients without scram (ATWS) events for light-water-cooled nuclear power plants.
(a) Applicability. The requirements of this section apply to all commercial light-water-cooled nuclear power plants, other than nuclear power reactor facilities for which the certifications required under § 50.82(a)(1) have been submitted.
(b) Definition. For purposes of this section, Anticipated Transient Without Scram (ATWS) means an anticipated operational occurrence as defined in appendix A of this part followed by the failure of the reactor trip portion of the protection system specified in General Design Criterion 20 of appendix A of this part.
(c) Requirements. (1) Each pressurized water reactor must have equipment from sensor output to final actuation device, that is diverse from the reactor trip system, to automatically initiate the auxiliary (or emergency) feedwater system and initiate a turbine trip under conditions indicative of an ATWS. This equipment must be designed to perform its function in a reliable manner and be independent (from sensor output to the final actuation device) from the existing reactor trip system.
(2) Each pressurized water reactor manufactured by Combustion Engineering or by Babcock and Wilcox must have a diverse scram system from the sensor output to interruption of power to the control rods. This scram system must be designed to perform its function in a reliable manner and be independent from the existing reactor trip system (from sensor output to interruption of power to the control rods).
(3) Each boiling water reactor must have an alternate rod injection (ARI) system that is diverse (from the reactor trip system) from sensor output to the final actuation device. The ARI system must have redundant scram air header exhaust valves. The ARI must be designed to perform its function in a reliable manner and be independent (from the existing reactor trip system) from sensor output to the final actuation device.
(4) Each boiling water reactor must have a standby liquid control system (SLCS) with the capability of injecting into the reactor pressure vessel a borated water solution at such a flow rate, level of boron concentration and boron-10 isotope enrichment, and accounting for reactor pressure vessel volume, that the resulting reactivity control is at least equivalent to that resulting from injection of 86 gallons per minute of 13 weight percent sodium pentaborate decahydrate solution at the natural boron-10 isotope abundance into a 251-inch inside diameter reactor pressure vessel for a given core design. The SLCS and its injection location must be designed to perform its function in a reliable manner. The SLCS initiation must be automatic and must be designed to perform its function in a reliable manner for plants granted a construction permit after July 26, 1984, and for plants granted a construction permit prior to July 26, 1984, that have already been designed and built to include this feature.
(5) Each boiling water reactor must have equipment to trip the reactor coolant recirculating pumps automatically under conditions indicative of an ATWS. This equipment must be designed to perform its function in a reliable manner.
(6) Information sufficient to demonstrate to the Commission the adequacy of items in paragraphs (c)(1) through (c)(5) of this section shall be submitted to the Commission as specified in § 50.4.
(d) Implementation. For each light-water-cooled nuclear power plant operating license issued before September 27, 2007, by 180 days after the issuance of the QA guidance for non-safety related components, each licensee shall develop and submit to the Commission, as specified in § 50.4, a proposed schedule for meeting the requirements of paragraphs (c)(1) through (c)(5) of this section. Each shall include an explanation of the schedule along with a justification if the schedule calls for final implementation later than the second refueling outage after July 26, 1984, or the date of issuance of a license authorizing operation above 5 percent of full power. A final schedule shall then be mutually agreed upon by the Commission and licensee. For each light-water-cooled nuclear power plant operating license application submitted after September 27, 2007, the applicant shall submit information in its final safety analysis report demonstrating how it will comply with paragraphs (c)(1) through (c)(5) of this section.
[49 FR 26044, June 26, 1984; 49 FR 27736, July 6, 1984, as amended at 51 FR 40310, Nov. 6, 1986; 54 FR 13362, Apr. 3, 1989; 61 FR 39301, July 29, 1996; 72 FR 49500, Aug. 28, 2007]

Title 10 published on 2012-01-01

The following are only the Rules published in the Federal Register after the published date of Title 10.

For a complete list of all Rules, Proposed Rules, and Notices view the Rulemaking tab.

  • 2013-01-04; vol. 78 # 3 - Friday, January 4, 2013
    1. 78 FR 663 - Decommissioning Planning During Operations
      GPO FDSys XML | Text
      NUCLEAR REGULATORY COMMISSION
      Regulatory guide; issuance.
      10 CFR Parts 20, 30, 40, 50, 70, and 72

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code
U.S.C. : Title 42 - THE PUBLIC HEALTH AND WELFARE

§ 2131 - License required

§ 2132 - Utilization and production facilities for industrial or commercial purposes

§ 2133 - Commercial licenses

§ 2134 - Medical, industrial, and commercial licenses

§ 2135 - Antitrust provisions governing licenses

§ 2138 - Suspension of licenses during war or national emergency

§ 2152 - Policies contained in international arrangements

§ 2232 - License applications

§ 2233 - Terms of licenses

§ 2234 - Inalienability of licenses

§ 2236 - Revocation of licenses

§ 2237 - Modification of license

§ 2239 - Hearings and judicial review

§ 2282 - Civil penalties

§ 4332 - Cooperation of agencies; reports; availability of information; recommendations; international and national coordination of efforts

§ 5842 - Licensing and related regulatory functions respecting selected Administration facilities

§ 5844 - Office of Nuclear Safety and Safeguards

§ 5846 - Compliance with safety regulations

Statutes at Large

119 Stat. 594

92 Stat. 2951

Title 10 published on 2012-01-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 10 CFR 50 after this date.

  • 2013-04-10; vol. 78 # 69 - Wednesday, April 10, 2013
    1. 78 FR 21275 - Station Blackout Mitigation Strategies
      GPO FDSys XML | Text
      NUCLEAR REGULATORY COMMISSION
      Draft regulatory basis and draft rule concepts; request for comment.
      Submit comments by May 28, 2013. Comments received after this date will be considered if it is practical to do so, but the NRC is only able to ensure consideration of comments received on or before this date.
      10 CFR Parts 50 and 52