10 CFR 600.250 - Closeout.

§ 600.250 Closeout.
(a) General. The Federal agency will close out the award when it determines that all applicable administrative actions and all required work of the grant has been completed.
(b) Reports. Within 90 days after the expiration or termination of the grant, the grantee must submit all financial, performance, and other reports required as a condition of the grant. Upon request by the grantee, Federal agencies may extend this timeframe. These may include but are not limited to:
(1) Final performance or progress report.
(2) Financial Status Report (SF 269) or Outlay Report and Request for Reimbursement for Construction Programs (SF-271) (as applicable).
(3) Final request for payment (SF-270) (if applicable).
(4) Invention disclosure (if applicable).
(5) Federally-owned property report:
In accordance with § 600.232(f), a grantee must submit an inventory of all federally owned property (as distinct from property acquired with grant funds) for which it is accountable and request disposition instructions from the Federal agency of property no longer needed.
(c) Cost adjustment. The Federal agency will, within 90 days after receipt of reports in paragraph (b) of this section, make upward or downward adjustments to the allowable costs.
(d) Cash adjustments.
(1) The Federal agency will make prompt payment to the grantee for allowable reimbursable costs.
(2) The grantee must immediately refund to the Federal agency any balance of unobligated (unencumbered) cash advanced that is not authorized to be retained for use on other grants.
[53 FR 8045, 8087, Mar. 11, 1988. Redesignated at 59 FR 53264, Oct. 21, 1994, as amended at 61 FR 7166, Feb. 26, 1996]

Title 10 published on 2014-01-01

no entries appear in the Federal Register after this date.

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code

Title 10 published on 2014-01-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 10 CFR 600 after this date.

  • 2014-05-15; vol. 79 # 94 - Thursday, May 15, 2014
    1. 79 FR 27795 - Administrative Requirements for Grants and Cooperative Agreements
      GPO FDSys XML | Text
      DEPARTMENT OF ENERGY
      Notice of proposed rulemaking and opportunity for public comment.
      DOE will accept comments, data, and information regarding this notice of proposed rulemaking (NOPR) no later than July 14, 2014.
      10 CFR Part 600