§ 602.8 Application requirements.
(a) An original and seven copies of the application for initial support must be submitted, except that State and local governments and Indian tribal governments shall not be required to submit more than the original and two copies of the application.
(b) Each new or renewal application in response to this part must include:
(1) An application face page, DOE Form 4650.2 (approved by OMB under OMB Control No. 1910-1400). However, the face page of an application submitted by a State or local government or an Indian tribal government shall be the face page of Standard Form 424 (approved by OMB under OMB Control Number 0348-0043).
(2) A detailed description of the proposed project, including its objectives, its relationship to DOE's program, its impact on the environment, if any, and the applicant's plan for carrying it out.
(3) Detailed information about the background and experience of the recipients of funds or, as appropriate, the principal investigator(s) (including references to publications), the facilities and experience of the applicant, and the cost-sharing arrangements, if any.
(4) A detailed budget for the entire proposed period of support with written justification sufficient to evaluate the itemized list of costs provided on the entire project. Applicants should note the following when preparing budgets:
(i) Numerical details on items of cost provided by State and local government and Indian tribal government applicants shall be on Standard Form 424A, “Budget Information for Non-Construction Programs” (approved under OMB Control No. 0348-0044). All other applicants shall use budget forms ERF 4620.1 (approved by OMB under Control No. 1910-1400).
(ii) DOE may, subsequent to receipt of an application, request additional budgetary information from an applicant when necessary for clarification or make informed pre-award determinations under 10 CFR part 600.
(5) Any pre-award assurances required pursuant to 10 CFR parts 600 and 602.
(c) Applications for a renewal award must be submitted with an original and seven copies, except that State and local governments and Indian tribal government applicants are required to submit only an original and two copies (Approved by OMB under OMB Control Numbers 0348-00050348-0009)
(d) The application must be signed by an official who is authorized to act for the applicant organization and to commit the applicant to comply with the terms and conditions of the award, if one is issued, or if unaffiliated, by the individual applicant. (See § 602.17(a)(1) for requirements on continuation awards.)
(e) DOE may return an application that does not include all information and documentation required by statute, this part, 10 CFR part 600, or the notice of availability, when the nature of the omission precludes review of the application.
(f) During the review of a complete application, DOE may request the submission of additional information only if the information is essential to evaluate the application.
(g) In addition to including the information described in paragraphs (b), (c), and (d) of this section, an application for a renewal award must be submitted no later than 6 months before the expiration of the project period and must be on the same forms as required for initial applications. The renewal application must outline and justify a program and budget for the proposed project period, showing in detail the estimated cost of the proposed project, together with an indication of the amount of cost sharing, if any. The application shall also describe and explain the reasons for any change in the scope or objectives of the proposed project and shall compare and explain any difference between the estimates in the proposed budget and actual costs experienced as of the date of the application.
(h) DOE is not required to return an application to the applicant.
(i) Renewal applications must include a separate section that describes the results of work accomplished through the date of the renewal application and how such results relate to the activities proposed to be undertaken in the renewal period.

Title 10 published on 2014-01-01

The following are only the Rules published in the Federal Register after the published date of Title 10.

For a complete list of all Rules, Proposed Rules, and Notices view the Rulemaking tab.

  • 2014-12-19; vol. 79 # 244 - Friday, December 19, 2014
    1. 79 FR 75872 - Federal Awarding Agency Regulatory Implementation of Office of Management and Budget's Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards
      GPO FDSys XML | Text
      DEPARTMENT OF STATE, DEPARTMENT OF VETERANS AFFAIRS, DEPARTMENT OF EDUCATION, DEPARTMENT OF JUSTICE, SMALL BUSINESS ADMINISTRATION, DEPARTMENT OF HOUSING AND URBAN DEVELOPMENT, AGENCY FOR INTERNATIONAL DEVELOPMENT, NATIONAL SCIENCE FOUNDATION, CORPORATION FOR NATIONAL AND COMMUNITY SERVICE, NATIONAL ARCHIVES AND RECORDS ADMINISTRATION, DEPARTMENT OF TREASURY, NATIONAL ENDOWMENT FOR THE ARTS, DEPARTMENT OF TRANSPORTATION, GULF COAST ECOSYSTEM RESTORATION COUNCIL, DEPARTMENT OF HEALTH AND HUMAN SERVICES, EXECUTIVE OFFICE OF THE PRESIDENT, DEPARTMENT OF LABOR, ENVIRONMENTAL PROTECTION AGENCY, INSTITUTE OF MUSEUM AND LIBRARY SERVICES, DEPARTMENT OF DEFENSE, NATIONAL ENDOWMENT FOR THE HUMANITIES, NATIONAL AERONAUTICS AND SPACE ADMINISTRATION, DEPARTMENT OF THE INTERIOR, DEPARTMENT OF COMMERCE, DEPARTMENT OF AGRICULTURE, DEPARTMENT OF ENERGY, DEPARTMENT OF HOMELAND SECURITY, SOCIAL SECURITY ADMINISTRATION, Federal Emergency Management Agency, National Institute of Food and Agriculture, Rural Utilities Service, Rural Housing Service, Office of the Chief Financial Officer, Farm Service Agency, Office of National Drug Control Policy, Office of Management and Budget, Commodity Credit Corporation, Rural Business-Cooperative Service
      Interim final rule.
      Effective date: This interim final rule is effective on December 26, 2014. The incorporation by reference of certain publications listed in the rule is approved by the Director of the Federal Register as of December 26, 2014. Implementation dates: For grants authorized under the Robert T. Stafford Disaster Relief and Emergency Assistance Act, this rule is applicable for emergency or major disaster declarations issued on or after December 26, 2014. For non-Federal entities that are nonprofit organizations or institutions of higher education (IHEs), there is a one-year grace period for implementation of the procurement standards in 2 CFR 200.317 through 200.326. As will be detailed in the 2015 OMB Compliance Supplement, non-Federal entities choosing to delay implementation for the procurement standards will need to specify in their documented policies and procedures that they continue to comply with OMB circular A-110 for one additional fiscal year which begins after December 26, 2014. Comment date: To be assured of consideration, comments must be received by OMB electronically through www.regulations.gov no later than midnight Eastern Standard Time (E.S.T.) on February 17, 2015.
      2 CFR Parts 1, 25, 170, 180, and 200

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code
U.S. Code: Title 31 - MONEY AND FINANCE
U.S. Code: Title 42 - THE PUBLIC HEALTH AND WELFARE

§ 2051 - Research and development assistance

§ 5817 - Powers of Administrator

§ 5901 - Congressional statement of findings

§ 5902 - Congressional declaration of policy and purpose; implementation and administration of program by Secretary of Energy

§ 5903 - Duties and authorities of the Secretary

§ 5903a - Nonduplication of programs, projects, and research facilities

§ 5903b - Environmental and safety research, development, and demonstration program

§ 5903c - Moneys received by Secretary from fossil energy activity; payment into Treasury; reports to House and Senate Committees

§ 5903d - Clean coal technology projects; proposals, implementation, funding, etc.

§ 5904 - Research, development, and demonstration program governing principles

§ 5905 - Comprehensive planning and programming

§ 5906 - Federal assistance and participation in programs

§ 5907 - Demonstration projects

§ 5907a - Small grant program

§ 5908 - Patents and inventions

§ 5909 - Relationship to antitrust laws

§ 5910 - Repealed.

§ 5911 - Acquisition of essential materials

§ 5912 - Water resource assessments

§ 5913 - Evaluation by National Institute of Standards and Technology of energy-related inventions prior to awarding of grants by Secretary; promulgation of regulations

§ 5914 - Omitted

§ 5915 - Authorization of appropriations

§ 5915a - Expiration of initial authorization to construct fossil energy demonstration plants

§ 5916 - Central source of nonnuclear energy information

§ 5917 - Repealed.

§ 5918 - Repealed.

§ 5920 - Repealed.

§ 7254 - Rules and regulations

§ 7256 - Contracts, leases, etc., with public agencies and private organizations and persons

Title 10 published on 2014-01-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 10 CFR 602 after this date.

  • 2014-12-19; vol. 79 # 244 - Friday, December 19, 2014
    1. 79 FR 75872 - Federal Awarding Agency Regulatory Implementation of Office of Management and Budget's Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards
      GPO FDSys XML | Text
      DEPARTMENT OF STATE, DEPARTMENT OF VETERANS AFFAIRS, DEPARTMENT OF EDUCATION, DEPARTMENT OF JUSTICE, SMALL BUSINESS ADMINISTRATION, DEPARTMENT OF HOUSING AND URBAN DEVELOPMENT, AGENCY FOR INTERNATIONAL DEVELOPMENT, NATIONAL SCIENCE FOUNDATION, CORPORATION FOR NATIONAL AND COMMUNITY SERVICE, NATIONAL ARCHIVES AND RECORDS ADMINISTRATION, DEPARTMENT OF TREASURY, NATIONAL ENDOWMENT FOR THE ARTS, DEPARTMENT OF TRANSPORTATION, GULF COAST ECOSYSTEM RESTORATION COUNCIL, DEPARTMENT OF HEALTH AND HUMAN SERVICES, EXECUTIVE OFFICE OF THE PRESIDENT, DEPARTMENT OF LABOR, ENVIRONMENTAL PROTECTION AGENCY, INSTITUTE OF MUSEUM AND LIBRARY SERVICES, DEPARTMENT OF DEFENSE, NATIONAL ENDOWMENT FOR THE HUMANITIES, NATIONAL AERONAUTICS AND SPACE ADMINISTRATION, DEPARTMENT OF THE INTERIOR, DEPARTMENT OF COMMERCE, DEPARTMENT OF AGRICULTURE, DEPARTMENT OF ENERGY, DEPARTMENT OF HOMELAND SECURITY, SOCIAL SECURITY ADMINISTRATION, Federal Emergency Management Agency, National Institute of Food and Agriculture, Rural Utilities Service, Rural Housing Service, Office of the Chief Financial Officer, Farm Service Agency, Office of National Drug Control Policy, Office of Management and Budget, Commodity Credit Corporation, Rural Business-Cooperative Service
      Interim final rule.
      Effective date: This interim final rule is effective on December 26, 2014. The incorporation by reference of certain publications listed in the rule is approved by the Director of the Federal Register as of December 26, 2014. Implementation dates: For grants authorized under the Robert T. Stafford Disaster Relief and Emergency Assistance Act, this rule is applicable for emergency or major disaster declarations issued on or after December 26, 2014. For non-Federal entities that are nonprofit organizations or institutions of higher education (IHEs), there is a one-year grace period for implementation of the procurement standards in 2 CFR 200.317 through 200.326. As will be detailed in the 2015 OMB Compliance Supplement, non-Federal entities choosing to delay implementation for the procurement standards will need to specify in their documented policies and procedures that they continue to comply with OMB circular A-110 for one additional fiscal year which begins after December 26, 2014. Comment date: To be assured of consideration, comments must be received by OMB electronically through www.regulations.gov no later than midnight Eastern Standard Time (E.S.T.) on February 17, 2015.
      2 CFR Parts 1, 25, 170, 180, and 200