10 CFR 602, Appendix A to Part 602 - Schedule of Renewal Applications and Reports

prev | next
Pt. 602, App. A
Appendix A to Part 602—Schedule of Renewal Applications and Reports
Type When due Number of copies for awarding office
1. Summary: 200 words on scope and purpose (Notice of Energy R&D Project) Immediately after a grant is awarded and with each application for renewal 3
2. Renewal period ends 6 months before the budget 8
3. Progress Report period (or as part of a renewal application) 90 days prior to the next budget period 3
4. Other progress reports, brief topical reports, etc. (Designated when significant results develop or when work has direct programmatic impact) As deemed appropriate by DOE or the recipient 3
5. Reprints, Conference Same as 4. above 3
6. Final report of the project Within 90 days after completion 3
7. Financial Status Report (FSR) Within 90 days after completion of the project period; for budget periods exceeding 12 months an FSR is also required within 90 days after the first 12-month period 3
Note: Report types 5 and 6 require with submission two copies of DOE Form 1332.16, University-Type Contractor and Grantee Recommendations for Disposition of Scientific and Technical Document.

Title 10 published on 2012-01-01

no entries appear in the Federal Register after this date.

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.