10 CFR 71.10 - Public inspection of application.

§ 71.10 Public inspection of application.
Applications for approval of a package design under this part, which are submitted to the Commission, may be made available for public inspection, in accordance with provisions of parts 2 and 9 of this chapter. This includes an application to amend or revise an existing package design, any associated documents and drawings submitted with the application, and any responses to NRC requests for additional information.

Title 10 published on 2014-01-01

no entries appear in the Federal Register after this date.

Title 10 published on 2014-01-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 10 CFR 71 after this date.

  • 2014-02-11; vol. 79 # 28 - Tuesday, February 11, 2014
    1. 79 FR 8097 - Deliberate Misconduct Rule and Hearings on Challenges to the Immediate Effectiveness of Orders
      GPO FDSys XML | Text
      NUCLEAR REGULATORY COMMISSION
      Proposed rule.
      Submit comments by May 12, 2014. Comments received after this date will be considered if it is practical to do so. However, the NRC is able to ensure consideration only of comments received on or before this date.