10 CFR 71.107 - Package design control.

Status message

There is 1 rule appearing in the Federal Register for 10 CFR 71. View below or at eCFR (GPOAccess)
§ 71.107 Package design control.
(a) The licensee, certificate holder, and applicant for a CoC shall establish measures to assure that applicable regulatory requirements and the package design, as specified in the license or CoC for those materials and components to which this section applies, are correctly translated into specifications, drawings, procedures, and instructions. These measures must include provisions to assure that appropriate quality standards are specified and included in design documents and that deviations from standards are controlled. Measures must be established for the selection and review for suitability of application of materials, parts, equipment, and processes that are essential to the functions of the materials, parts, and components of the packaging that are important to safety.
(b) The licensee, certificate holder, and applicant for a CoC shall establish measures for the identification and control of design interfaces and for coordination among participating design organizations. These measures must include the establishment of written procedures, among participating design organizations, for the review, approval, release, distribution, and revision of documents involving design interfaces. The design control measures must provide for verifying or checking the adequacy of design, by methods such as design reviews, alternate or simplified calculational methods, or by a suitable testing program. For the verifying or checking process, the licensee shall designate individuals or groups other than those who were responsible for the original design, but who may be from the same organization. Where a test program is used to verify the adequacy of a specific design feature in lieu of other verifying or checking processes, the licensee, certificate holder, and applicant for a CoC shall include suitable qualification testing of a prototype or sample unit under the most adverse design conditions. The licensee, certificate holder, and applicant for a CoC shall apply design control measures to the following:
(1) Criticality physics, radiation shielding, stress, thermal, hydraulic, and accident analyses;
(2) Compatibility of materials;
(3) Accessibility for inservice inspection, maintenance, and repair;
(4) Features to facilitate decontamination; and
(5) Delineation of acceptance criteria for inspections and tests.
(c) The licensee, certificate holder, and applicant for a CoC shall subject design changes, including field changes, to design control measures commensurate with those applied to the original design. Changes in the conditions specified in the CoC require prior NRC approval.

Title 10 published on 2014-01-01

The following are only the Rules published in the Federal Register after the published date of Title 10.

For a complete list of all Rules, Proposed Rules, and Notices view the Rulemaking tab.

  • 2014-11-10; vol. 79 # 217 - Monday, November 10, 2014
    1. 79 FR 66598 - Miscellaneous Corrections
      GPO FDSys XML | Text
      NUCLEAR REGULATORY COMMISSION
      Final rule.
      This rule is effective on December 10, 2014.
      10 CFR Parts 2, 15, 19, 20, 26, 30, 40, 50, 51, 52, 55, 60, 61, 63, 70, 71, 72, 73, and 76

Title 10 published on 2014-01-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 10 CFR 71 after this date.

  • 2014-11-10; vol. 79 # 217 - Monday, November 10, 2014
    1. 79 FR 66598 - Miscellaneous Corrections
      GPO FDSys XML | Text
      NUCLEAR REGULATORY COMMISSION
      Final rule.
      This rule is effective on December 10, 2014.
      10 CFR Parts 2, 15, 19, 20, 26, 30, 40, 50, 51, 52, 55, 60, 61, 63, 70, 71, 72, 73, and 76