10 CFR 71.115 - Control of purchased material, equipment, and services.

§ 71.115 Control of purchased material, equipment, and services.
(a) The licensee, certificate holder, and applicant for a CoC shall establish measures to assure that purchased material, equipment, and services, whether purchased directly or through contractors and subcontractors, conform to the procurement documents. These measures must include provisions, as appropriate, for source evaluation and selection, objective evidence of quality furnished by the contractor or subcontractor, inspection at the contractor or subcontractor source, and examination of products on delivery.
(b) The licensee, certificate holder, and applicant for a CoC shall have available documentary evidence that material and equipment conform to the procurement specifications before installation or use of the material and equipment. The licensee, certificate holder, and applicant for a CoC shall retain, or have available, this documentary evidence for the life of the package to which it applies. The licensee, certificate holder, and applicant for a CoC shall assure that the evidence is sufficient to identify the specific requirements met by the purchased material and equipment.
(c) The licensee, certificate holder, and applicant for a CoC shall assess the effectiveness of the control of quality by contractors and subcontractors at intervals consistent with the importance, complexity, and quantity of the product or services.

Title 10 published on 2014-01-01

no entries appear in the Federal Register after this date.

Title 10 published on 2014-01-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 10 CFR 71 after this date.

  • 2014-02-11; vol. 79 # 28 - Tuesday, February 11, 2014
    1. 79 FR 8097 - Deliberate Misconduct Rule and Hearings on Challenges to the Immediate Effectiveness of Orders
      GPO FDSys XML | Text
      NUCLEAR REGULATORY COMMISSION
      Proposed rule.
      Submit comments by May 12, 2014. Comments received after this date will be considered if it is practical to do so. However, the NRC is able to ensure consideration only of comments received on or before this date.
      10 CFR Parts 2, 30, 40, 50, 52, 60, 61, 63, 70, 71, 72, 76, 110, and 150