10 CFR 72.82 - Inspections and tests.

Status message

There are 7 Updates appearing in the Federal Register for 10 CFR 72. View below or at eCFR (GPOAccess)
§ 72.82 Inspections and tests.
(a) Each licensee under this part shall permit duly authorized representatives of the Commission to inspect its records, premises, and activities and of spent fuel, high-level radioactive waste, or reactor-related GTCC waste in its possession related to the specific license as may be necessary to meet the objectives of the Act, including section 105 of the Act.
(b) Each licensee under this part shall make available to the Commission for inspection, upon reasonable notice, records kept by the licensee pertaining to its receipt, possession, packaging, or transfer of spent fuel, high-level radioactive waste, or reactor-related GTCC waste.
(c)
(1) Each licensee under this part shall upon request by the Director, Office of Nuclear Material Safety and Safeguards or the appropriate NRC Regional Administrator provide rent-free office space for the exclusive use of the Commission inspection personnel. Heat, air conditioning, light, electrical outlets and janitorial services shall be furnished by each licensee. The office shall be convenient to and have full access to the installation and shall provide the inspector both visual and acoustic privacy.
(2) For a site with a single storage installation the space provided shall be adequate to accommodate a full-time inspector, a part-time secretary, and transient NRC personnel and will be generally commensurate with other office facilities at the site. A space of 250 sq. ft., either within the site's office complex or in an office trailer, or other onsite space, is suggested as a guide. For sites containing multiple facilities, additional space may be requested to accommodate additional full-time inspectors. The office space that is provided shall be subject to the approval of the Director, Office of Nuclear Material Safety and Safeguards or the appropriate NRC Regional Administrator. All furniture, supplies and Commission equipment will be furnished by the Commission.
(3) Each licensee under this part shall afford any NRC resident inspector assigned to that site, or other NRC inspectors identified by the Regional Administrator as likely to inspect the installation, immediate unfettered access, equivalent to access provided regular plant employees, following proper identification and compliance with applicable access control measures for security, radiological protection, and personal safety.
(d) Each licensee shall perform, or permit the Commission to perform, such tests as the Commission deems appropriate or necessary for the administrator of the regulations in this part.
[53 FR 31658, Aug. 19, 1988, as amended at 64 FR 17512, Apr. 12, 1999; 66 FR 51842, Oct. 11, 2001]

Title 10 published on 2014-01-01

The following are only the Rules published in the Federal Register after the published date of Title 10.

For a complete list of all Rules, Proposed Rules, and Notices view the Rulemaking tab.

  • 2014-07-31; vol. 79 # 147 - Thursday, July 31, 2014
    1. 79 FR 44264 - List of Approved Spent Fuel Storage Casks: Transnuclear, Inc. NUHOMS® HD Cask System, Certificate of Compliance No. 1030, Amendment No. 2
      GPO FDSys XML | Text
      NUCLEAR REGULATORY COMMISSION
      Direct final rule.
      The final rule is effective October 14, 2014, unless significant adverse comments are received by September 2, 2014 in response to the companion proposed rule published elsewhere in this issue of the Federal Register . Please see the companion proposed rule for detailed instructions on submitting comments. If this direct final rule is withdrawn as a result of such comments, timely notice of the withdrawal will be published in the Federal Register . Comments received after this date will be considered if it is practical to do so, but the NRC staff is able to ensure consideration only for comments received on or before this date.
      10 CFR Part 72

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code
U.S. Code: Title 42 - THE PUBLIC HEALTH AND WELFARE

§ 2021 - Cooperation with States

§ 2071 - Determination of other material as special nuclear material; Presidential assent; effective date

§ 2073 - Domestic distribution of special nuclear material

§ 2077 - Unauthorized dealings in special nuclear material

§ 2092 - License requirements for transfers

§ 2093 - Domestic distribution of source material

§ 2095 - Reports

§ 2099 - Prohibitions against issuance of license

§ 2111 - Domestic distribution

§ 2201 - General duties of Commission

§ 2232 - License applications

§ 2233 - Terms of licenses

§ 2234 - Inalienability of licenses

§ 2236 - Revocation of licenses

§ 2238 - Continued operation of facilities

§ 2239 - Hearings and judicial review

§ 2282 - Civil penalties

§ 4332 - Cooperation of agencies; reports; availability of information; recommendations; international and national coordination of efforts

§ 5841 - Establishment and transfers

§ 5842 - Licensing and related regulatory functions respecting selected Administration facilities

§ 5846 - Compliance with safety regulations

§ 5851 - Employee protection

§ 10101 - Definitions

§ 10102 - Separability

§ 10103 - Territories and possessions

§ 10104 - Ocean disposal

§ 10105 - Limitation on spending authority

§ 10106 - Protection of classified national security information

§ 10107 - Applicability to atomic energy defense activities

§ 10108 - Applicability to transportation

§ 10137 - Consultation with States and affected Indian tribes

§ 10151 - Findings and purposes

§ 10152 - Available capacity for interim storage of spent nuclear fuel

§ 10153 - Interim at-reactor storage

§ 10154 - Licensing of facility expansions and transshipments

§ 10155 - Storage of spent nuclear fuel

§ 10157 - Transportation

§ 10161 - Monitored retrievable storage

§ 10162 - Authorization of monitored retrievable storage

§ 10165 - Site selection

§ 10168 - Construction authorization

§ 10198 - Research and development on spent nuclear fuel

U.S. Code: Title 44 - PUBLIC PRINTING AND DOCUMENTS
Statutes at Large

Title 10 published on 2014-01-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 10 CFR 72 after this date.

  • 2014-07-31; vol. 79 # 147 - Thursday, July 31, 2014
    1. 79 FR 44264 - List of Approved Spent Fuel Storage Casks: Transnuclear, Inc. NUHOMS® HD Cask System, Certificate of Compliance No. 1030, Amendment No. 2
      GPO FDSys XML | Text
      NUCLEAR REGULATORY COMMISSION
      Direct final rule.
      The final rule is effective October 14, 2014, unless significant adverse comments are received by September 2, 2014 in response to the companion proposed rule published elsewhere in this issue of the Federal Register . Please see the companion proposed rule for detailed instructions on submitting comments. If this direct final rule is withdrawn as a result of such comments, timely notice of the withdrawal will be published in the Federal Register . Comments received after this date will be considered if it is practical to do so, but the NRC staff is able to ensure consideration only for comments received on or before this date.
      10 CFR Part 72