10 CFR 74.41 - Nuclear material control and accounting for special nuclear material of moderate strategic significance.

Status message

There is 1 rule appearing in the Federal Register for 10 CFR 74. View below or at eCFR (GPOAccess)
prev | next
§ 74.41 Nuclear material control and accounting for special nuclear material of moderate strategic significance.
(a) General performance objectives. Each licensee who is authorized to possess special nuclear material (SNM) of moderate strategic significance or SNM in a quantity exceeding one effective kilogram of strategic special nuclear material in irradiated fuel reprocessing operations other than as sealed sources and to use this material at any site other than a nuclear reactor licensed pursuant to part 50 of this chapter; or as reactor irradiated fuels involved in research, development, and evaluation programs in facilities other than irradiated fuel reprocessing plants; or an operation involved with waste disposal, shall establish, implement, and maintain a Commission-approved material control and accounting (MC&A) system that will achieve the following performance objectives:
(1) Maintain accurate, current, and reliable information on, and confirm, the quantities and locations of SNM in the licensee's possession;
(2) Conduct investigations and resolve any anomalies indicating a possible loss of special nuclear material;
(3) Permit rapid determination of whether an actual loss of a significant quantity of SNM has occurred, with significant quantity being either:
(i) More than one formula kilogram of strategic SNM; or
(ii) 10,000 grams or more of uranium-235 contained in uranium enriched up to 20.00 percent.
(4) Generate information to aid in the investigation and recovery of missing SNM in the event of an actual loss.
(b) Implementation schedule. Each applicant for a license, and each licensee that, upon application for modification of its license, would become newly subject to the requirements of paragraph (a) of this section shall:
(1) Submit a fundamental nuclear material control (FNMC) plan describing how the performance objectives of § 74.41(a) will be achieved, and how the system capabilities required by § 74.41(c) will be met; and
(2) Implement the NRC-approved FNMC plan submitted pursuant to paragraph (b)(1) of this section upon the Commission's issuance or modification of a license or by the date specified in a license condition.
(c) System capabilities. To achieve the performance objectives specified in § 74.41(a), the MC&A system must include the capabilities described in §§ 74.43 and 74.45, and must incorporate checks and balances that are sufficient to detect falsification of data and reports that could conceal diversion of SNM by:
(1) A single individual, including an employee in any position; or
(2) Collusion between two individuals, one or both of whom have authorized access to SNM.
[67 FR 78146, Dec. 23, 2002]

Title 10 published on 2014-01-01

The following are only the Rules published in the Federal Register after the published date of Title 10.

For a complete list of all Rules, Proposed Rules, and Notices view the Rulemaking tab.

  • 2014-12-19; vol. 79 # 244 - Friday, December 19, 2014
    1. 79 FR 75735 - Organizational Changes and Conforming Amendments
      GPO FDSys XML | Text
      NUCLEAR REGULATORY COMMISSION
      Final rule.
      This final rule is effective on December 19, 2014.
      10 CFR Parts 1, 2, 30, 31, 32, 34, 35, 37, 40, 51, 61, 62, 70, 71, 72, 73, 74, 75, 140, and 150

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code

Title 10 published on 2014-01-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 10 CFR 74 after this date.

  • 2014-12-19; vol. 79 # 244 - Friday, December 19, 2014
    1. 79 FR 75735 - Organizational Changes and Conforming Amendments
      GPO FDSys XML | Text
      NUCLEAR REGULATORY COMMISSION
      Final rule.
      This final rule is effective on December 19, 2014.
      10 CFR Parts 1, 2, 30, 31, 32, 34, 35, 37, 40, 51, 61, 62, 70, 71, 72, 73, 74, 75, 140, and 150