10 CFR 75.15 - Facility attachments.

Status message

There is 1 rule appearing in the Federal Register for 10 CFR 75. View below or at eCFR (GPOAccess)
prev | next
§ 75.15 Facility attachments.
(a) The Facility Attachment or Transitional Facility Attachment will document the determinations referred to in § 75.10 and will contain other appropriate provisions.
(b) The Commission will issue license or certificate amendments, as necessary, to implement the Safeguards Agreement and the Facility Attachment (as amended from time to time). The license or certificate amendments through reference to the Facility Attachment or Transitional Facility Attachment, or otherwise, will specify:
(1) IAEA material balance areas;
(2) Types of modifications for which information is required, under § 75.10, to be submitted in advance;
(3) Procedures, as referred to in § 75.21;
(4) The extent to which isotopic composition must be included in batch data (under § 75.22) and advance notification (§ 75.45);
(5) Items to be reported in the concise notes accompanying inventory change reports, as referred to in § 75.34;
(6) Loss limits and changes in containment, as referred to in § 75.36 (pertaining to special reports);
(7) Actions required to be taken under § 75.8(f) at the request of an IAEA inspector;
(8) Procedures to be used for documentation of requests under § 75.46 (pertaining to expenses); and
(9) Other appropriate matters.
(c) The Commission will also issue license or certificate amendments, as necessary, for implementing the Initial Protocol to the Safeguards Agreement and the Transitional Facility Attachment (as amended from time to time).
(d) License or certificate amendments will be made under the Commission's rules of practice (part 2 of this chapter). Specifically, if the licensee or certificate holder does not agree to an amendment, an order modifying the license would be issued under § 2.204 of this chapter.
(e) Subject to constraints imposed by the Safeguards Agreement, the Commission will afford the applicant, licensee, or certificate holder a reasonable opportunity to participate in the development of the Facility Attachment or Transitional Facility Attachment applicable to the facility, and any amendments thereto, and to review and comment upon any instrument before it has been agreed to by the United States. The Commission will provide to the applicant, licensee, or certificate holder a copy of any such instrument that has been completed under the Safeguards Agreement.
(f) Locations reporting under the Additional Protocol, unless located in a facility selected under Article 39(b) of the main text of the Safeguards Agreement, do not have Facility Attachments or Transitional Facility Attachments.
[73 FR 78612, Dec. 23, 2008]

Title 10 published on 2014-01-01

The following are only the Rules published in the Federal Register after the published date of Title 10.

For a complete list of all Rules, Proposed Rules, and Notices view the Rulemaking tab.

  • 2014-12-19; vol. 79 # 244 - Friday, December 19, 2014
    1. 79 FR 75735 - Organizational Changes and Conforming Amendments
      GPO FDSys XML | Text
      NUCLEAR REGULATORY COMMISSION
      Final rule.
      This final rule is effective on December 19, 2014.
      10 CFR Parts 1, 2, 30, 31, 32, 34, 35, 37, 40, 51, 61, 62, 70, 71, 72, 73, 74, 75, 140, and 150

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code

Title 10 published on 2014-01-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 10 CFR 75 after this date.

  • 2014-12-19; vol. 79 # 244 - Friday, December 19, 2014
    1. 79 FR 75735 - Organizational Changes and Conforming Amendments
      GPO FDSys XML | Text
      NUCLEAR REGULATORY COMMISSION
      Final rule.
      This final rule is effective on December 19, 2014.
      10 CFR Parts 1, 2, 30, 31, 32, 34, 35, 37, 40, 51, 61, 62, 70, 71, 72, 73, 74, 75, 140, and 150