§ 75.2 Scope.
(a) All persons licensed by the Nuclear Regulatory Commission or an Agreement State, or who hold a certificate of compliance, or construction permit or authorization issued by the Nuclear Regulatory Commission are subject to the requirements of this part. These requirements also apply to all persons who have filed an application with the NRC to construct a facility or to receive source or special nuclear material. Locations determined by the U.S. Government to be associated with activities or information of direct national security significance to the United States are excluded from these requirements. Specifically, these requirements pertain to the following locations and activities of licensees and certificate holders:
(1) A facility, as defined in § 75.4, and the site of the facility;
(2) A location performing nuclear fuel cycle-related research and development, as defined in § 75.4;
(3) A location manufacturing, assembling, or constructing nuclear fuel cycle-related equipment or materials as defined in § 75.4;
(4) A location of a uranium or thorium mine or concentration plant (e.g., in-situ leach mines and activities involving ore processing);
(5) A location importing or possessing “impure” source material [i.e., source material not in the form of purified chemical products (e.g., UF6, U metal, UO2)];
(6) A location possessing source or special nuclear material on which IAEA safeguards have been exempted or terminated;
(7) A location receiving imports of material or equipment that is subject to export controls; and
(8) The activity of exporting source materials for non-nuclear purposes or exporting of non-nuclear material or equipment that is subject to export controls.
(b) Facilities referred to in § 75.2(a)(1) are also subject to the reporting requirements of § 75.6(b) and (c), IAEA inspections in § 75.8, Facility information in § 75.10, and the Material Accounting and Control requirements in §§ 75.21 through 75.45.
(c) Locations referred to in § 75.2(a)(2) through 75.2(a)(7) are also subject to the reporting requirements of § 75.6(b) and (d), and IAEA inspections in § 75.8, and location information in § 75.11.
[73 FR 78607, Dec. 23, 2008]

Title 10 published on 2014-01-01

The following are only the Rules published in the Federal Register after the published date of Title 10.

For a complete list of all Rules, Proposed Rules, and Notices view the Rulemaking tab.

  • 2014-12-19; vol. 79 # 244 - Friday, December 19, 2014
    1. 79 FR 75735 - Organizational Changes and Conforming Amendments
      GPO FDSys XML | Text
      NUCLEAR REGULATORY COMMISSION
      Final rule.
      This final rule is effective on December 19, 2014.
      10 CFR Parts 1, 2, 30, 31, 32, 34, 35, 37, 40, 51, 61, 62, 70, 71, 72, 73, 74, 75, 140, and 150

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code

Title 10 published on 2014-01-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 10 CFR 75 after this date.

  • 2014-12-19; vol. 79 # 244 - Friday, December 19, 2014
    1. 79 FR 75735 - Organizational Changes and Conforming Amendments
      GPO FDSys XML | Text
      NUCLEAR REGULATORY COMMISSION
      Final rule.
      This final rule is effective on December 19, 2014.
      10 CFR Parts 1, 2, 30, 31, 32, 34, 35, 37, 40, 51, 61, 62, 70, 71, 72, 73, 74, 75, 140, and 150