10 CFR 900.4 - Pre-Application mechanism.

§ 900.4 Pre-Application mechanism.
(a) An applicant, or prospective applicant, for a Federal authorization seeking information from a permitting entity pursuant to 16 U.S.C. 824p(h)(4)(C) must request information pursuant to the terms specified in this section with a permitting entity, and notify the Director of the request to the permitting entity.
(b) Any request for information filed under this section shall specify in sufficient detail the information sought from the permitting entity and shall contain sufficient information for the permitting entity to provide the requested information pursuant to 16 U.S.C. 824p(h)(4)(C).
(c) Within 60 days of receipt of such a request for information, a permitting entity shall provide, to the extent permissible under existing law, information concerning the request to the applicant, or prospective applicant, and the Director.

Title 10 published on 2014-01-01

no entries appear in the Federal Register after this date.

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code