§ 1408.24 Waiver of procedural requirements.
(a) The Corporation may impose offset against a payment to be made to a debtor prior to the completion of the procedures required by this part, if:
(1) Failure to impose the offset would substantially prejudice the Government's ability to collect the debt; and
(2) The timing of the payment against which the offset will be imposed does not reasonably permit the completion of those procedures.
(b) The procedures required by this part shall be complied with promptly after the offset is imposed. Amounts recovered by offset, which are later found not to be owed to the Government, shall be promptly refunded to the debtor.

Title 12 published on 2014-01-01

no entries appear in the Federal Register after this date.

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code