§ 125.23 What is the process for such an appeal?
(a) Notice of appeal. When the contacting officer rejects a recommendation by SBA's Procurement Center Representative to make a requirement available for award as an SDVO contract, he or she must notify the Procurement Center Representative as soon as practicable. If the Administrator intends to appeal the decision, SBA must notify the contracting officer no later than five business days after receiving notice of the contracting officer's decision.
(b) Suspension of action. Upon receipt of notice of SBA's intent to appeal, the contracting officer must suspend further action regarding the procurement until the Secretary of the department or head of the agency issues a written decision on the appeal, unless the Secretary of the department or head of the agency makes a written determination that urgent and compelling circumstances which significantly affect the interests of the United States compel award of the contract.
(c) Deadline for appeal. Within 15 business days of SBA's notification to the CO, SBA must file its formal appeal with the Secretary of the department or head of the agency, or the appeal will be deemed withdrawn.
(d) Decision. The Secretary of the department or head of the agency must specify in writing the reasons for a denial of an appeal brought under this section.

Title 13 published on 2014-01-01

The following are only the Rules published in the Federal Register after the published date of Title 13.

For a complete list of all Rules, Proposed Rules, and Notices view the Rulemaking tab.

  • 2014-06-03; vol. 79 # 106 - Tuesday, June 3, 2014
    1. 79 FR 31848 - Acquisition Process: Task and Delivery Order Contracts, Bundling, Consolidation; Correction
      GPO FDSys XML | Text
      SMALL BUSINESS ADMINISTRATION
      Correcting amendments.
      Effective June 3, 2014.
      13 CFR Parts 125 and 127

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code

Title 13 published on 2014-01-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 13 CFR 125 after this date.

  • 2014-06-03; vol. 79 # 106 - Tuesday, June 3, 2014
    1. 79 FR 31848 - Acquisition Process: Task and Delivery Order Contracts, Bundling, Consolidation; Correction
      GPO FDSys XML | Text
      SMALL BUSINESS ADMINISTRATION
      Correcting amendments.
      Effective June 3, 2014.
      13 CFR Parts 125 and 127