15 CFR 700.16 - Changes or cancellations of priority ratings and rated orders.
§ 700.16
Changes or cancellations of priority ratings and rated orders.
(b)
If an unrated order is amended so as to make it a rated order, or a DO, rating is changed to a DX rating, the supplier must give the appropriate preferential treatment to the order as of the date the change is received by the supplier.
(c)
An amendment to a rated order that significantly alters a supplier's original production or delivery schedule shall constitute a new rated order as of the date of its receipt. The supplier must accept or reject the amended order according to the provisions of § 700.13.
(d)
The following amendments do not constitute a new rated order: a change in shipping destination; a reduction in the total amount of the order; an increase in the total amount of the order which has negligible impact upon deliveries; a minor variation in size or design; or a change which is agreed upon between the supplier and the customer.
Title 15 published on 2012-01-01
no entries appear in the Federal Register after this date.
This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.
This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].
It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.
Executive Order ... 12656
Executive Order ... 12742
Executive Order ... 12919
Executive Order ... 13286