§ 157.211 Delivery points.
(a) Construction and operation—
(1) Automatic authorization. The certificate holder may acquire, construct, replace, modify, or operate any delivery point, excluding the construction of certain delivery points subject to the prior notice provisions in paragraph (a)(2) of this section if:
(i) The natural gas is being delivered to, or for the account of, a shipper for whom the certificate holder is, or will be, authorized to transport gas; and
(ii) The certificate holder's tariff does not prohibit the addition of new delivery points.
(2) Prior notice. Subject to the notice procedure in § 157.205, the certificate holder may acquire, construct, replace, modify, or operate any delivery point if:
(i) The natural gas is being delivered to, or for the account of, an end-user that is currently being served by a local distribution company; and
(ii) The natural gas is being delivered to a shipper for whom the certificate holder is, or will be, authorized to transport gas; and
(iii) The certificate holder's tariff does not prohibit the addition of new delivery points.
(b) Contents of request. In addition to the requirements of § 157.205(b), requests for activities authorized under paragraph (a)(2) must contain:
(1) The name of the end-user, the location of the delivery point, and the distribution company currently serving the end-user;
(2) A description of the facility and any appurtenant facilities;
(3) A USGS 71/2-minute series (scale 1:24,000 or 1:25,000) topographic map (or map of equivalent or greater detail, as appropriate) showing the location of the proposed facilities;
(4) The quantity of gas to be delivered through the proposed facility;
(5) A description, with supporting data, of the impact of the service rendered through the proposed delivery tap upon the certificate holder's peak day and annual deliveries.
(c) Reporting requirements. As part of the certificate holder's annual report of projects authorized under paragraph (a) of this section, the certificate holder must report in the manner prescribed in §§ 157.6(a) and 385.2011 of this chapter:
(1) A description of the facilities acquired, constructed, replaced, modified or operated pursuant to this section;
(2) The location and maximum quantities delivered at such delivery point;
(3) The actual cost and the completion date of the delivery point; and
(4) The date of each agreement obtained pursuant to § 157.206(b)(3) and the date construction began.
[Order 436, 50 FR 42491, Oct. 18, 1985, as amended by Order 493, 53 FR 15030, Apr. 27, 1988; Order 603, 64 FR 26608, May 14, 1999; Order 603-B, 65 FR 11464, Mar. 3, 2000]

Title 18 published on 2014-04-01

The following are only the Rules published in the Federal Register after the published date of Title 18.

For a complete list of all Rules, Proposed Rules, and Notices view the Rulemaking tab.

  • 2014-11-25; vol. 79 # 227 - Tuesday, November 25, 2014
    1. 79 FR 70056 - Revisions to Auxiliary Installations, Replacement Facilities, and Siting and Maintenance Regulations
      GPO FDSys XML | Text
      DEPARTMENT OF ENERGY, Federal Energy Regulatory Commission
      Final rule; order on rehearing and clarification.
      This rule is effective January 26, 2015.
      18 CFR Parts 2, 157, and 380

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code

Title 18 published on 2014-04-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 18 CFR 157 after this date.

  • 2014-11-25; vol. 79 # 227 - Tuesday, November 25, 2014
    1. 79 FR 70056 - Revisions to Auxiliary Installations, Replacement Facilities, and Siting and Maintenance Regulations
      GPO FDSys XML | Text
      DEPARTMENT OF ENERGY, Federal Energy Regulatory Commission
      Final rule; order on rehearing and clarification.
      This rule is effective January 26, 2015.