§ 157.33 Requirement for open season.
(a) Any application for a certificate of public convenience and necessity or other authorization for a proposed Alaska natural gas transportation project must include a demonstration that the applicant has conducted an open season for capacity on its proposed project, in accordance with the requirements of this subpart. Failure to provide the requisite demonstration will result in an application being rejected as incomplete.
(b) Initial capacity on a proposed Alaska natural gas transportation project may be acquired prior to an open season through pre-subscription agreements, provided that in any open season as required in paragraph (a) of this section, capacity is offered to all prospective bidders at the same rates and on the same terms and conditions as contained in the pre-subscription agreements. All pre-subscription agreements shall be made public by posting on Internet websites and press releases within ten days of their execution. In the event there is more than one such agreement, all prospective bidders shall be allowed the option of selecting among the several agreements all of the rates, terms and conditions contained in any one such agreement.
[Order 2005, 70 FR 8286, Feb. 18, 2005, as amended by Order 2005-A, 70 FR 35026, June 16, 2005]

Title 18 published on 2013-04-01

The following are only the Rules published in the Federal Register after the published date of Title 18.

For a complete list of all Rules, Proposed Rules, and Notices view the Rulemaking tab.

  • 2014-02-05; vol. 79 # 24 - Wednesday, February 5, 2014
    1. 79 FR 6808 - Natural Gas Pipelines; Project Cost and Annual Limits
      GPO FDSys XML | Text
      DEPARTMENT OF ENERGY, Federal Energy Regulatory Commission
      Final rule.
      This final rule is effective February 5, 2014 and establishes cost limits applicable from January 1, 2014 through December 31, 2014.
      18 CFR Part 157

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code

Title 18 published on 2013-04-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 18 CFR 157 after this date.

  • 2014-02-05; vol. 79 # 24 - Wednesday, February 5, 2014
    1. 79 FR 6808 - Natural Gas Pipelines; Project Cost and Annual Limits
      GPO FDSys XML | Text
      DEPARTMENT OF ENERGY, Federal Energy Regulatory Commission
      Final rule.
      This final rule is effective February 5, 2014 and establishes cost limits applicable from January 1, 2014 through December 31, 2014.