18 CFR 157.38 - Pre-approval procedures.

Status message

There is 1 rule appearing in the Federal Register for 18 CFR 157. View below or at eCFR (GPOAccess)
§ 157.38 Pre-approval procedures.
No later than 90 days prior to providing the notice of open season required by § 157.34(a), a prospective applicant must file, for Commission approval, a detailed plan for conducting an open season in conformance with this subpart. The prospective applicant's plan shall include the proposed notice of open season. Upon receipt of a request for such a determination, the Secretary of the Commission shall issue a notice of the request, which will then be published in the Federal Register. The notice shall establish a date on which comments from interested persons are due and a date, which shall be within 60 days of receipt of the prospective applicant's request unless otherwise directed by the Commission, by which the Commission will act on the proposed plan.
[Order 2005-A, 70 FR 35026, June 16, 2005]

Title 18 published on 2014-04-01

The following are only the Rules published in the Federal Register after the published date of Title 18.

For a complete list of all Rules, Proposed Rules, and Notices view the Rulemaking tab.

  • 2014-11-25; vol. 79 # 227 - Tuesday, November 25, 2014
    1. 79 FR 70056 - Revisions to Auxiliary Installations, Replacement Facilities, and Siting and Maintenance Regulations
      GPO FDSys XML | Text
      DEPARTMENT OF ENERGY, Federal Energy Regulatory Commission
      Final rule; order on rehearing and clarification.
      This rule is effective January 26, 2015.
      18 CFR Parts 2, 157, and 380

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code

Title 18 published on 2014-04-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 18 CFR 157 after this date.

  • 2014-11-25; vol. 79 # 227 - Tuesday, November 25, 2014
    1. 79 FR 70056 - Revisions to Auxiliary Installations, Replacement Facilities, and Siting and Maintenance Regulations
      GPO FDSys XML | Text
      DEPARTMENT OF ENERGY, Federal Energy Regulatory Commission
      Final rule; order on rehearing and clarification.
      This rule is effective January 26, 2015.
      18 CFR Parts 2, 157, and 380