§ 157.9 Notice of application and notice of schedule for environmental review.
(a) Notice of each application filed, except when rejected in accordance with § 157.8, will be issued within 10 business days of filing, and subsequently will be published in the Federal Register and copies of such notice sent to States affected thereby, by electronic means if practical, otherwise by mail. Persons desiring to receive a copy of the notice of every application shall so advise the Secretary.
(b) For each application that will require an environmental assessment or an environmental impact statement, notice of a schedule for the environmental review will be issued within 90 days of the notice of the application, and subsequently will be published in the Federal Register.
[Order 653, 70 FR 8724, Feb. 23, 2005, as amended by Order 687, 71 FR 62920, Oct. 27, 2006]

Title 18 published on 2013-04-01

The following are only the Rules published in the Federal Register after the published date of Title 18.

For a complete list of all Rules, Proposed Rules, and Notices view the Rulemaking tab.

  • 2014-02-05; vol. 79 # 24 - Wednesday, February 5, 2014
    1. 79 FR 6808 - Natural Gas Pipelines; Project Cost and Annual Limits
      GPO FDSys XML | Text
      DEPARTMENT OF ENERGY, Federal Energy Regulatory Commission
      Final rule.
      This final rule is effective February 5, 2014 and establishes cost limits applicable from January 1, 2014 through December 31, 2014.
      18 CFR Part 157

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code

Title 18 published on 2013-04-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 18 CFR 157 after this date.

  • 2014-02-05; vol. 79 # 24 - Wednesday, February 5, 2014
    1. 79 FR 6808 - Natural Gas Pipelines; Project Cost and Annual Limits
      GPO FDSys XML | Text
      DEPARTMENT OF ENERGY, Federal Energy Regulatory Commission
      Final rule.
      This final rule is effective February 5, 2014 and establishes cost limits applicable from January 1, 2014 through December 31, 2014.