Skip to main content
 

18 CFR 157, Subpart D - Exemption of Natural Gas Service for Drilling, Testing, or Purging from Certificate Requirements

There are 3 Updates appearing in the Federal Register for 18 CFR 157. Select the tab below to view, or View eCFR (GPOAccess)

Title 18 published on 2012-04-01

The following are only the Rules published in the Federal Register after the published date of Title 18.

For a complete list of all Rules, Proposed Rules, and Notices view the Rulemaking tab.

  • 2013-02-06; vol. 78 # 25 - Wednesday, February 6, 2013
    1. 78 FR 8389 - Natural Gas Pipelines; Project Cost and Annual Limits
      GPO FDSys XML | Text
      DEPARTMENT OF ENERGY, Federal Energy Regulatory Commission
      Final rule.
      This final rule is effective February 6, 2013 and establishes cost limits applicable from January 1, 2013 through December 31, 2013.
      18 CFR Part 157

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code
USC : Title 15 - COMMERCE AND TRADE

§ 717 - Regulation of natural gas companies

§ 717a - Definitions

§ 717b - Exportation or importation of natural gas; LNG terminals

15 USC § 717b–1 - State and local safety considerations

§ 717c - Rates and charges

15 USC § 717c–1 - Prohibition on market manipulation

§ 717d - Fixing rates and charges; determination of cost of production or transportation

§ 717e - Ascertainment of cost of property

§ 717f - Construction, extension, or abandonment of facilities

§ 717g - Accounts; records; memoranda

§ 717h - Rates of depreciation

§ 717i - Periodic and special reports

§ 717j - State compacts for conservation, transportation, etc., of natural gas

§ 717k - Officials dealing in securities

15 USC § -

§ 717m - Investigations by Commission

§ 717n - Process coordination; hearings; rules of procedure

15 USC § -

§ 717p - Joint boards

§ 717q - Appointment of officers and employees

§ 717r - Rehearing and review

§ 717s - Enforcement of chapter

§ 717t - General penalties

15 USC § 717t–1 - Civil penalty authority

15 USC § 717t–2 - Natural gas market transparency rules

§ 717u - Jurisdiction of offenses; enforcement of liabilities and duties

§ 717v - Separability

§ 717w - Short title

Title 18 published on 2012-04-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 18 CFR 157 after this date.

  • 2013-02-06; vol. 78 # 25 - Wednesday, February 6, 2013
    1. 78 FR 8389 - Natural Gas Pipelines; Project Cost and Annual Limits
      GPO FDSys XML | Text
      DEPARTMENT OF ENERGY, Federal Energy Regulatory Commission
      Final rule.
      This final rule is effective February 6, 2013 and establishes cost limits applicable from January 1, 2013 through December 31, 2013.
      18 CFR Part 157