§ 35.19a
Refund requirements under suspension orders.
(a) Refunds. (1) The public utility whose proposed increased rates or charges were suspended shall refund at such time in such amounts and in such manner as required by final order of the Commission the portion of any increased rates or charges found by the Commission in that suspension proceeding not to be justified, together with interest as required in paragraph (a)(2) of this section.
(2) Interest shall be computed from the date of collection until the date refunds are made as follows:
(i) At a rate of seven percent simple interest per annum on all excessive rates or charges held prior to October 10, 1974;
(ii) At a rate of nine percent simple interest per annum on all excessive rates or charges held between October 10, 1974, and September 30, 1979; and
(iii) (A) At an average prime rate for each calendar quarter on all excessive rates or charges held (including all interest applicable to such rates or charges) on or after October 1, 1979. The applicable average prime rate for each calendar quarter shall be the arithmetic mean, to the nearest one-hundredth of one percent, of the prime rate values published in the Federal Reserve Bulletin, or in the Federal Reserve's “Selected Interest Rates” (Statistical Release H. 15), for the fourth, third, and second months preceding the first month of the calendar quarter.
(B) The interest required to be paid under clause (iii)(A) shall be compounded quarterly.
(3) Any public utility required to make refunds pursuant to this section shall bear all costs of such refunding.
(b) Reports. Any public utility whose proposed increased rates or charges were suspended and have gone into effect pending final order of the Commission pursuant to section 205(e) of the Federal Power Act shall keep accurate account of all amounts received under the increased rates or charges which became effective after the suspension period, for each billing period, specifying by whom and in whose behalf such amounts are paid.
[44 FR 53503, Sept. 14, 1979, as amended at 45 FR 3889, Jan. 21, 1980; Order 545, 57 FR 53990, Nov. 16, 1992; 74 FR 54463, Oct. 22, 2009]

Title 18 published on 2012-04-01

The following are only the Rules published in the Federal Register after the published date of Title 18.

For a complete list of all Rules, Proposed Rules, and Notices view the Rulemaking tab.

  • 2013-01-25; vol. 78 # 17 - Friday, January 25, 2013
    1. 78 FR 5268 - Allocation of Capacity on New Merchant Transmission Projects and New Cost-Based, Participant-Funded Transmission Projects; Priority Rights to New Participant-Funded Transmission
      GPO FDSys XML | Text
      DEPARTMENT OF ENERGY, Federal Energy Regulatory Commission
      Final Policy Statement.
      These policies became effective January 17, 2013.
      18 CFR Parts 2 and 35

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code
USC : Title 16 - CONSERVATION

§ 791 - Repealed. Aug. 26, 1935, ch. 687, title II,

§ 791a - Short title

§ 792 - Federal Power Commission; creation; number; appointment; term; qualifications; vacancies; quorum; chairman; salary; place of holding sessions

§ 793 - Appointment of officers and employees of Commission; duties, and salaries; detail of officers and employees from other departments; expenditures authorized

§ 793a - Repealed.

§ 794, 795 - Omitted

§ 796 - Definitions

§ 797 - General powers of Commission

§ 797a - Congressional authorization for permits, licenses, leases, or authorizations for dams, conduits, reservoirs, etc., within national parks or monuments

§ 797b - Duty to keep Congress fully and currently informed

§ 797c - Dams in National Park System units

§ 797d - Third party contracting by FERC

§ 798 - Purpose and scope of preliminary permits; transfer and cancellation

§ 799 - License; duration, conditions, revocation, alteration, or surrender

§ 800 - Issuance of preliminary permits or licenses

§ 801 - Transfer of license; obligations of transferee

§ 802 - Information to accompany application for license; landowner notification

§ 803 - Conditions of license generally

§ 804 - Project works affecting navigable waters; requirements insertable in license

§ 805 - Participation by Government in costs of locks, etc.

§ 806 - Time limit for construction of project works; extension of time; termination or revocation of licenses for delay

§ 807 - Right of Government to take over project works

§ 808 - New licenses and renewals

§ 809 - Temporary use by Government of project works for national safety; compensation for use

§ 810 - Disposition of charges arising from licenses

§ 811 - Operation of navigation facilities; rules and regulations; penalties

§ 812 - Public-service licensee; regulations by State or by commission as to service, rates, charges, etc.

§ 813 - Power entering into interstate commerce; regulation of rates, charges, etc.

§ 814 - Exercise by licensee of power of eminent domain

§ 815 - Contract to furnish power extending beyond period of license; obligations of new licensee

§ 816 - Preservation of rights vested prior to June 10, 1920

§ 817 - Projects not affecting navigable waters; necessity for Federal license, permit or right-of-way; unauthorized activities

§ 818 - Public lands included in project; reservation of lands from entry

§ 819 - Repealed. Aug. 26, 1935, ch. 687, title II,

§ 820 - Proceedings for revocation of license or to prevent violations of license

§ 821 - State laws and water rights unaffected

§ 822 - Reservation of right to alter or repeal chapter

§ 823 - Repeal of inconsistent laws

§ 823a - Conduit hydroelectric facilities

§ 823b - Enforcement

§ 823c - Alaska State jurisdiction over small hydroelectric projects

§ 823d - Alternative conditions and prescriptions

§ 824 - Declaration of policy; application of subchapter

§ 824a - Interconnection and coordination of facilities; emergencies; transmission to foreign countries

16 USC § 824a–1 - Pooling

16 USC § 824a–2 - Reliability

16 USC § 824a–3 - Cogeneration and small power production

16 USC § 824a–4 - Seasonal diversity electricity exchange

§ 824b - Disposition of property; consolidations; purchase of securities

§ 824c - Issuance of securities; assumption of liabilities

§ 824d - Rates and charges; schedules; suspension of new rates; automatic adjustment clauses

§ 824e - Power of Commission to fix rates and charges; determination of cost of production or transmission

§ 824f - Ordering furnishing of adequate service

§ 824g - Ascertainment of cost of property and depreciation

§ 824h - References to State boards by Commission

§ 824i - Interconnection authority

§ 824j - Wheeling authority

16 USC § 824j–1 - Open access by unregulated transmitting utilities

§ 824k - Orders requiring interconnection or wheeling

16 USC § -

§ 824m - Sales by exempt wholesale generators

§ 824n - Repealed.

16 USC § -

§ 824p - Siting of interstate electric transmission facilities

§ 824q - Native load service obligation

§ 824r - Protection of transmission contracts in the Pacific Northwest

§ 824s - Transmission infrastructure investment

§ 824t - Electricity market transparency rules

§ 824u - Prohibition on filing false information

§ 824v - Prohibition of energy market manipulation

§ 824w - Joint boards on economic dispatch

§ 825 - Accounts and records

§ 825a - Rates of depreciation; notice to State authorities before fixing

§ 825b - Requirements applicable to agencies of United States

§ 825c - Periodic and special reports; obstructing filing reports or keeping accounts, etc.

§ 825d - Officials dealing in securities

§ 825e - Complaints

§ 825f - Investigations by Commission

§ 825g - Hearings; rules of procedure

§ 825h - Administrative powers of Commission; rules, regulations, and orders

§ 825i - Appointment of officers and employees; compensation

§ 825j - Investigations relating to electric energy; reports to Congress

§ 825k - Publication and sale of reports

16 USC § -

§ 825m - Enforcement provisions

§ 825n - Forfeiture for violations; recovery; applicability

16 USC § -

16 USC § -

§ 825p - Jurisdiction of offenses; enforcement of liabilities and duties

§ 825q - Repealed.

16 USC § 825q–1 - Office of Public Participation

§ 825r - Separability

§ 2601 - Findings

§ 2602 - Definitions

§ 2603 - Relationship to antitrust laws

§ 2611 - Purposes

§ 2612 - Coverage

§ 2613 - Federal contracts

§ 2621 - Consideration and determination respecting certain ratemaking standards

§ 2622 - Obligations to consider and determine

§ 2623 - Adoption of certain standards

§ 2624 - Lifeline rates

§ 2625 - Special rules for standards

§ 2626 - Reports respecting standards

§ 2627 - Relationship to State law

§ 2631 - Intervention in proceedings

§ 2632 - Consumer representation

§ 2633 - Judicial review and enforcement

§ 2634 - Prior and pending proceedings

§ 2641 - Voluntary guidelines

§ 2642 - Responsibilities of Secretary

§ 2643 - Gathering information on costs of service

§ 2644 - Relationship to other authority

§ 2645 - Utility regulatory institute

USC : Title 31 - MONEY AND FINANCE

§ 9701 - Fees and charges for Government services and things of value

Title 18 published on 2012-04-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 18 CFR 35 after this date.

  • 2013-03-29; vol. 78 # 61 - Friday, March 29, 2013
    1. 78 FR 19149 - Small Generator Interconnection Agreements and Procedures; Supplemental Notice of Workshop
      GPO FDSys XML | Text
      DEPARTMENT OF ENERGY, Federal Energy Regulatory Commission
      Supplemental notice of workshop.
      The conference will be convened from 9:30 a.m. to approximately 5:00 p.m. (EDT).
      18 CFR Part 35