Skip to main content
 

18 CFR 37.5 - Obligations of Transmission Providers and Responsible Parties.

§ 37.5
Obligations of Transmission Providers and Responsible Parties.
(a) Each Transmission Provider is required to provide for the operation of an OASIS, either individually or jointly with other Transmission Providers, in accordance with the requirements of this Part. The Transmission Provider may delegate this responsibility to a Responsible Party such as another Transmission Provider, an Independent System Operator, a Regional Transmission Group, or a Regional Reliability Council.
(b) A Responsible Party must provide access to an OASIS providing standardized information relevant to the availability of transmission capacity, prices, and other information (as described in this part) pertaining to the transmission system for which it is responsible.
(c) A Responsible Party may not deny or restrict access to an OASIS user merely because that user makes automated computer-to-computer file transfers or queries, or extensive requests for data.
(d) In the event that an OASIS user's grossly inefficient method of accessing an OASIS node or obtaining information from the node seriously degrades the performance of the node, a Responsible Party may limit a user's access to the OASIS node without prior Commission approval. The Responsible Party must immediately contact the OASIS user to resolve the problem. Notification of the restriction must be made to the Commission within two business days of the incident and include a description of the problem. A closure report describing how the problem was resolved must be filed with the Commission within one week of the incident.
(e) In the event that an OASIS user makes an error in a query, the Responsible Party can block the affected query and notify the user of the nature of the error. The OASIS user must correct the error before making any additional queries. If there is a dispute over whether an error has occurred, the procedures in paragraph (d) of this section apply.
(f) Transmission Providers must provide “read only” access to the OASIS to Commission staff and the staffs of State regulatory authorities, at no cost, after such staff members have complied with the requisite registration procedures.
[Order 889, 61 FR 21764, May 10, 1996, as amended by Order 605, 64 FR 34124, June 25, 1999; Order 638, 65 FR 17400, Mar. 31, 2000; Order 676, 71 FR 26212, May 4, 2006]

Title 18 published on 2012-04-01

no entries appear in the Federal Register after this date.

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code
USC : Title 16 - CONSERVATION

§ 791 - Repealed. Aug. 26, 1935, ch. 687, title II,

§ 791a - Short title

§ 792 - Federal Power Commission; creation; number; appointment; term; qualifications; vacancies; quorum; chairman; salary; place of holding sessions

§ 793 - Appointment of officers and employees of Commission; duties, and salaries; detail of officers and employees from other departments; expenditures authorized

§ 793a - Repealed.

§ 794, 795 - Omitted

§ 796 - Definitions

§ 797 - General powers of Commission

§ 797a - Congressional authorization for permits, licenses, leases, or authorizations for dams, conduits, reservoirs, etc., within national parks or monuments

§ 797b - Duty to keep Congress fully and currently informed

§ 797c - Dams in National Park System units

§ 797d - Third party contracting by FERC

§ 798 - Purpose and scope of preliminary permits; transfer and cancellation

§ 799 - License; duration, conditions, revocation, alteration, or surrender

§ 800 - Issuance of preliminary permits or licenses

§ 801 - Transfer of license; obligations of transferee

§ 802 - Information to accompany application for license; landowner notification

§ 803 - Conditions of license generally

§ 804 - Project works affecting navigable waters; requirements insertable in license

§ 805 - Participation by Government in costs of locks, etc.

§ 806 - Time limit for construction of project works; extension of time; termination or revocation of licenses for delay

§ 807 - Right of Government to take over project works

§ 808 - New licenses and renewals

§ 809 - Temporary use by Government of project works for national safety; compensation for use

§ 810 - Disposition of charges arising from licenses

§ 811 - Operation of navigation facilities; rules and regulations; penalties

§ 812 - Public-service licensee; regulations by State or by commission as to service, rates, charges, etc.

§ 813 - Power entering into interstate commerce; regulation of rates, charges, etc.

§ 814 - Exercise by licensee of power of eminent domain

§ 815 - Contract to furnish power extending beyond period of license; obligations of new licensee

§ 816 - Preservation of rights vested prior to June 10, 1920

§ 817 - Projects not affecting navigable waters; necessity for Federal license, permit or right-of-way; unauthorized activities

§ 818 - Public lands included in project; reservation of lands from entry

§ 819 - Repealed. Aug. 26, 1935, ch. 687, title II,

§ 820 - Proceedings for revocation of license or to prevent violations of license

§ 821 - State laws and water rights unaffected

§ 822 - Reservation of right to alter or repeal chapter

§ 823 - Repeal of inconsistent laws

§ 823a - Conduit hydroelectric facilities

§ 823b - Enforcement

§ 823c - Alaska State jurisdiction over small hydroelectric projects

§ 823d - Alternative conditions and prescriptions

§ 824 - Declaration of policy; application of subchapter

§ 824a - Interconnection and coordination of facilities; emergencies; transmission to foreign countries

16 USC § 824a–1 - Pooling

16 USC § 824a–2 - Reliability

16 USC § 824a–3 - Cogeneration and small power production

16 USC § 824a–4 - Seasonal diversity electricity exchange

§ 824b - Disposition of property; consolidations; purchase of securities

§ 824c - Issuance of securities; assumption of liabilities

§ 824d - Rates and charges; schedules; suspension of new rates; automatic adjustment clauses

§ 824e - Power of Commission to fix rates and charges; determination of cost of production or transmission

§ 824f - Ordering furnishing of adequate service

§ 824g - Ascertainment of cost of property and depreciation

§ 824h - References to State boards by Commission

§ 824i - Interconnection authority

§ 824j - Wheeling authority

16 USC § 824j–1 - Open access by unregulated transmitting utilities

§ 824k - Orders requiring interconnection or wheeling

16 USC § -

§ 824m - Sales by exempt wholesale generators

§ 824n - Repealed.

16 USC § -

§ 824p - Siting of interstate electric transmission facilities

§ 824q - Native load service obligation

§ 824r - Protection of transmission contracts in the Pacific Northwest

§ 824s - Transmission infrastructure investment

§ 824t - Electricity market transparency rules

§ 824u - Prohibition on filing false information

§ 824v - Prohibition of energy market manipulation

§ 824w - Joint boards on economic dispatch

§ 825 - Accounts and records

§ 825a - Rates of depreciation; notice to State authorities before fixing

§ 825b - Requirements applicable to agencies of United States

§ 825c - Periodic and special reports; obstructing filing reports or keeping accounts, etc.

§ 825d - Officials dealing in securities

§ 825e - Complaints

§ 825f - Investigations by Commission

§ 825g - Hearings; rules of procedure

§ 825h - Administrative powers of Commission; rules, regulations, and orders

§ 825i - Appointment of officers and employees; compensation

§ 825j - Investigations relating to electric energy; reports to Congress

§ 825k - Publication and sale of reports

16 USC § -

§ 825m - Enforcement provisions

§ 825n - Forfeiture for violations; recovery; applicability

16 USC § -

16 USC § -

§ 825p - Jurisdiction of offenses; enforcement of liabilities and duties

§ 825q - Repealed.

16 USC § 825q–1 - Office of Public Participation

§ 825r - Separability

§ 2601 - Findings

§ 2602 - Definitions

§ 2603 - Relationship to antitrust laws

§ 2611 - Purposes

§ 2612 - Coverage

§ 2613 - Federal contracts

§ 2621 - Consideration and determination respecting certain ratemaking standards

§ 2622 - Obligations to consider and determine

§ 2623 - Adoption of certain standards

§ 2624 - Lifeline rates

§ 2625 - Special rules for standards

§ 2626 - Reports respecting standards

§ 2627 - Relationship to State law

§ 2631 - Intervention in proceedings

§ 2632 - Consumer representation

§ 2633 - Judicial review and enforcement

§ 2634 - Prior and pending proceedings

§ 2641 - Voluntary guidelines

§ 2642 - Responsibilities of Secretary

§ 2643 - Gathering information on costs of service

§ 2644 - Relationship to other authority

§ 2645 - Utility regulatory institute

USC : Title 31 - MONEY AND FINANCE

§ 9701 - Fees and charges for Government services and things of value

Title 18 published on 2012-04-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 18 CFR 37 after this date.

  • 2012-07-09; vol. 77 # 131 - Monday, July 9, 2012
    1. 77 FR 40414 - Third-Party Provision of Ancillary Services; Accounting and Financial Reporting for New Electric Storage Technologies
      GPO FDSys XML | Text
      DEPARTMENT OF ENERGY, Federal Energy Regulatory Commission
      Notice of Proposed Rulemaking.
      Comments are due 60 days after publication in the Federal Register .
      18 CFR Parts 35, 37, and 101