(a) Categorical exclusion means a category of actions described in § 380.4, which do not individually or cumulatively have a significant effect on the human environment and which the Commission has found to have no such effect and for which, therefore, neither an environmental assessment nor an environmental impact statement is required. The Commission may decide to prepare environmental assessments for the reasons stated in § 380.4(b).
(b) Commission means the Federal Energy Regulatory Commission.
(c) Council means the Council on Environmental Quality.
(d) Environmental assessment means a concise public document for which the Commission is responsible that serves to:
(1) Briefly provide sufficient evidence and analysis for determining whether to prepare an environmental impact statement or a finding of no significant impact.
(2) Aid the Commission's compliance with NEPA when no environmental impact statement is necessary.
(3) Facilitate preparation of a statement when one is necessary. Environmental assessments must include brief discussions of the need for the proposal, of alternatives as required by section 102(2 )(E) of NEPA, of the environmental impacts of the proposed action and alternatives, and a listing of agencies and persons consulted.
(e) Environmental impact statement (EIS) means a detailed written statement as required by section 102(2 )(C) of NEPA. DEIS means a draft EIS and FEIS means a final EIS.
(f) Environmental report or ER means that part of an application submitted to the Commission by an applicant for authorization of a proposed action which includes information concerning the environment, the applicant's analysis of the environmental impact of the action, or alternatives to the action required by this or other applicable statutes or regulations.
(g) Finding of no significant impact (FONSI) means a document by the Commission briefly presenting the reason why an action, not otherwise excluded by § 380.4, will not have a significant effect on the human environment and for which an environmental impact statement therefore will not be prepared. It must include the environmental assessment or a summary of it and must note other environmental documents related to it. If the assessment is included, the FONSI need not repeat any of the discussion in the assessment but may incorporate it by reference.
Title 18 published on 2012-04-01
no entries appear in the Federal Register after this date.
This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.
It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.
Executive Order ... 12009
Title 18 published on 2012-04-01
The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 18 CFR 380after this date.
DEPARTMENT OF ENERGY, Federal Energy Regulatory Commission
Notice of Proposed Rulemaking.
Comments are due March 5, 2013.
18 CFR Parts 2 and 380
The Natural Gas Act (NGA) requires that prior to the construction or extension of any natural gas facilities, the Federal Energy Regulatory Commission (Commission) must issue a certificate that authorizes a natural gas company to undertake the proposed activity. However, under the Commission's regulations, the construction of auxiliary installations or replacement facilities, while subject to the Commission's NGA jurisdiction, are not treated as the construction or extension of facilities, and thus do not require certificate authorization. The Commission proposes to revise its regulations to clarify that all activities related to the construction of auxiliary installations and replacement facilities must take place within a company's certificated right-of-way using previously approved work spaces. In addition, the Commission proposes to add landowner notification requirements for auxiliary installations, replacement facilities, and other jurisdictional activities performed within the right-of-way.