18 CFR 806.16 - Completeness of application.

prev | next
§ 806.16 Completeness of application.
(a) The Commission's staff shall review the application, and if necessary, request the project sponsor to provide any additional information that is deemed pertinent for proper evaluation of the project.
(b) An application deemed administratively incomplete will be returned to the project sponsor, who shall have 30 days to cure the administrative deficiencies. An application deemed technically deficient may be returned to the project sponsor, who shall have a period of time prescribed by Commission staff to cure the technical deficiencies. Failure to cure either administrative or technical deficiencies within the prescribed time may result in termination of the application process and forfeiture of any fees submitted.
(c) The project sponsor has a duty to provide information reasonably necessary for the Commission's review of the application. If the project sponsor fails to respond to the Commission's request for additional information, the Commission may terminate the application process, close the file and so notify the project sponsor. The project sponsor may reapply without prejudice by submitting a new application and fee.

Title 18 published on 2014-04-01

no entries appear in the Federal Register after this date.

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


Statutes at Large
Public Laws

91-575

Title 18 published on 2014-04-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 18 CFR 806 after this date.

  • 2014-09-26; vol. 79 # 187 - Friday, September 26, 2014
    1. 79 FR 57850 - Review and Approval of Projects
      GPO FDSys XML | Text
      SUSQUEHANNA RIVER BASIN COMMISSION
      Notice of proposed rulemaking and public hearing.
      Comments on these proposed rules may be submitted to the Commission on or before November 17, 2014. The Commission has scheduled a public hearing on the proposed rulemaking, to be held November 6, 2014, in Harrisburg, Pennsylvania. The location of the public hearing is listed in the ADDRESSES section of this document.
      18 CFR Part 806