18 CFR 806.5 - Projects that may require review and approval.

§ 806.5 Projects that may require review and approval.
(a) The following projects, if not otherwise requiring review and approval under § 806.4, and provided that the project sponsor is notified in writing by the Executive Director, may be subject to Commission review and approval as determined by the Commission or the Executive Director:
(1) Projects that may affect interstate water quality.
(2) Projects within a member state that have the potential to affect waters within another member state. This includes, but is not limited to, projects which have the potential to alter the physical, biological, chemical or hydrological characteristics of water resources of interstate streams designated by the Commission under separate resolution.
(3) Projects that may have a significant effect upon the comprehensive plan.
(4) Projects not included in paragraphs (a)(1) through (a)(3) of this section, but which could have an adverse, adverse cumulative, or interstate effect on the water resources of the basin.
(b) Determinations by the Executive Director may be appealed to the Commission within 30 days after receipt of notice of such determination as set forth in § 808.2.

Title 18 published on 2014-04-01

no entries appear in the Federal Register after this date.

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


Statutes at Large
Public Laws

91-575

Title 18 published on 2014-04-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 18 CFR 806 after this date.

  • 2014-09-26; vol. 79 # 187 - Friday, September 26, 2014
    1. 79 FR 57850 - Review and Approval of Projects
      GPO FDSys XML | Text
      SUSQUEHANNA RIVER BASIN COMMISSION
      Notice of proposed rulemaking and public hearing.
      Comments on these proposed rules may be submitted to the Commission on or before November 17, 2014. The Commission has scheduled a public hearing on the proposed rulemaking, to be held November 6, 2014, in Harrisburg, Pennsylvania. The location of the public hearing is listed in the ADDRESSES section of this document.
      18 CFR Part 806