23 CFR 627.5 - Applicable projects.

§ 627.5 Applicable projects.
(a) A VE analysis shall be conducted prior to the completion of final design on each applicable project that utilizes Federal-aid highway funding, and all approved recommendations shall be included in the project's plans, specifications and estimates.
(b) Applicable projects shall include the following:
(1) Each project located on the National Highway System (NHS) (as specified in 23 U.S.C. 103) where the estimated total project cost is $25 million or more that utilizes Federal-aid highway funding;
(2) Each bridge project located on or off of the NHS where the estimated total project cost is $20 million or more that utilizes Federal-aid highway funding;
(3) Any major project (as defined in 23 U.S.C. 106(h)), on or off of the NHS, that utilizes Federal-aid highway funding in any contract or phase comprising the major project;
(4) Any project for which a VE analysis has not been conducted and a change is made to the project's scope or design between the final design and the letting which results in an increase in the project's total cost exceeding the thresholds identified in paragraphs (b)(1), (2) or (3) of this section; and
(5) Any other Federal-aid project the FHWA determines to be appropriate.
(c) An additional VE analysis is not required if, after conducting the VE analysis required under this part for any project meeting the criteria of paragraph (b) of this section, the project is subsequently split into smaller projects in the design phase or if the project is programmed to be completed by the letting of multiple construction projects. However, the STA may not avoid the requirement to conduct a VE analysis on an applicable project by splitting the project into smaller projects, or multiple construction projects.
(d) The STA's VE Program's policies and procedures shall identify when any additional VE analysis should be considered or conducted in the planning and development of transportation projects.
(e) For projects utilizing design-build and other alternative project delivery methods for which final design is not complete prior to the release of the final request for proposals or other applicable solicitation documents, the estimated total cost for purposes of the thresholds identified in paragraphs (b)(1) and (2) of this section, shall be based on the best estimate of the cost to construct the project.

Title 23 published on 2014-04-01

no entries appear in the Federal Register after this date.

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code