23 CFR 636, Subpart A - General
prev | next
- § 636.101 — What does this part do?
- § 636.102 — Does this part apply to me?
- § 636.103 — What are the definitions of terms used in this part?
- § 636.104 — Does this part apply to all Federal-aid design-build projects?
- § 636.105 — Is the FHWA requiring the use of design-build?
- § 636.106 — [Reserved]
- § 636.107 — May contracting agencies use geographic preference in Federal-aid design-build or public-private partnership projects?
- § 636.108 — [Reserved]
- § 636.109 — How does the NEPA process relate to the design-build procurement process?
- § 636.110 — What procedures may be used for solicitations and receipt of proposals?
- § 636.111 — Can oral presentations be used during the procurement process?
- § 636.112 — May stipends be used?
- § 636.113 — Is the stipend amount eligible for Federal participation?
- § 636.114 — What factors should be considered in risk allocation?
- § 636.115 — May I meet with industry to gather information concerning the appropriate risk allocation strategies?
- § 636.116 — What organizational conflict of interest requirements apply to design-build projects?
- § 636.117 — What conflict of interest standards apply to individuals who serve as selection team members for the owner?
- § 636.118 — Is team switching allowed after contract award?
- § 636.119 — How does this part apply to a project developed under a public-private partnership?
Title 23 published on 2012-04-01
no entries appear in the Federal Register after this date.
This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.
This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].
It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.