24 CFR § 245.430 - Decision on request for approval.

§ 245.430 Decision on request for approval.

(a) After considering the mortgagor's request for approval and the materials submitted in connection with the request, HUD must notify the mortgagor in writing of its approval or disapproval of the proposed covered action, including, if applicable, its adjustment upward or downward of the proposed reduction in tenant-paid utilities. HUD must provide its reasons for its determination.

(b) The mortgagor must notify the tenants of HUD's decision in the manner provided in § 245.15. If HUD has approved the proposed covered action, the notice must state:

(1) The effective date of the covered action (which must be at least 30 days from the date of service of the notice and in accordance with the terms of existing leases);

(2) In the case of HUD's approval of a conversion from project-paid utilities to tenant-paid utilities or a reduction in tenant utility allowances, the amount of the rent to be paid to the mortgagor and the utility allowance for each unit; and

(3) In the case of HUD's approval of a conversion of residential units in a multifamily housing project to a nonresidential use or the transfer of the project to a cooperative housing mortgagor corporation or association, which residential rental units are to be converted and whether the conversion is to nonresidential use or to cooperative or condominium units.