25 CFR 170.460 - What must a project package include?

prev | next
§ 170.460 What must a project package include?
(a) The minimum requirements for a project package are:
(1) Plans;
(2) Specifications; and
(3) Estimates.
(b) In order to receive project approval the following additional items are required:
(1) A tribal resolution or other authorized document supporting the project;
(2) Right-of-way clearances;
(3) Required environmental, archeological, and cultural clearances; and
(4) Identification of design exceptions if used in the plans.
(c) A tribe may include additional items at its option.

Title 25 published on 2014-04-01

no entries appear in the Federal Register after this date.

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code