§ 1926.1000 Rollover protective structures (ROPS) for material handling equipment.
(a) Coverage.
(1) This section applies to the following types of material handling equipment: To all rubber-tired, self-propelled scrapers, rubber-tired front-end loaders, rubber-tired dozers, wheel-type agricultural and industrial tractors, crawler tractors, crawler-type loaders, and motor graders, with or without attachments, that are used in construction work. This requirement does not apply to sideboom pipelaying tractors.
(2) The promulgation of specific standards for rollover protective structures for compactors and rubber-tired skid-steer equipment is reserved pending consideration of standards currently being developed.
(b) Equipment manufactured on or after September 1, 1972. Material handling machinery described in paragraph (a) of this section and manufactured on or after September 1, 1972, shall be equipped with rollover protective structures which meet the minimum performance standards prescribed in §§ 1926.1001 and 1926.1002, as applicable.
(c) Equipment manufactured before September 1, 1972.
(1) All material handling equipment described in paragraph (a) of this section and manufactured or placed in service (owned or operated by the employer) prior to September 1, 1972, shall be fitted with rollover protective structures no later than the dates listed below:
(i) Machines manufactured on or after January 1, 1972, shall be fitted no later than April 1, 1973.
(ii) Machines manufactured between July 1, 1971, and December 31, 1971, shall be fitted no later than July 1, 1973.
(iii) Machines manufactured between July 1, 1970, and June 30, 1971, shall be fitted no later than January 1, 1974.
(iv) Machines manufactured between July 1, 1969, and June 30, 1970, shall be fitted no later than July 1, 1974.
(v) Machines manufactured before July 1, 1969: Reserved pending further study, development, and review.
(2) Rollover protective structures and supporting attachment shall meet the minimum performance criteria detailed in §§ 1926.1001 and 1926.1002, as applicable or shall be designed, fabricated, and installed in a manner which will support, based on the ultimate strength of the metal, at least two times the weight of the prime mover applied at the point of impact.
(i) The design objective shall be to minimize the likelihood of a complete overturn and thereby minimize the possibility of the operator being crushed as a result of a rollover or upset.
(ii) The design shall provide a vertical clearance of at least 52 inches from the work deck to the ROPS at the point of ingress or egress.
(d) Remounting. ROPS removed for any reason, shall be remounted with equal quality, or better, bolts or welding as required for the original mounting.
(e) Labeling. Each ROPS shall have the following information permanently affixed to the structure:
(1) Manufacturer or fabricator's name and address;
(2) ROPS model number, if any;
(3) Machine make, model, or series number that the structure is designed to fit.
(f) Machines meeting certain existing governmental requirements. Any machine in use, equipped with rollover protective structures, shall be deemed in compliance with this section if it meets the rollover protective structure requirements of the State of California, the U.S. Army Corps of Engineers, or the Bureau of Reclamation of the U.S. Department of the Interior in effect on April 5, 1972. The requirements in effect are:
(1) State of California: Construction Safety Orders, issued by the Department of Industrial Relations pursuant to Division 5, Labor Code, § 6312, State of California.
(2) U.S. Army Corps of Engineers: General Safety Requirements, EM-385-1-1 (March 1967).
(3) Bureau of Reclamation, U.S. Department of the Interior: Safety and Health Regulations for Construction. Part II (September 1971).

Title 29 published on 2013-07-01

The following are only the Rules published in the Federal Register after the published date of Title 29.

For a complete list of all Rules, Proposed Rules, and Notices view the Rulemaking tab.

  • 2014-04-11; vol. 79 # 70 - Friday, April 11, 2014
    1. 79 FR 20316 - Electric Power Generation, Transmission, and Distribution; Electrical Protective Equipment
      GPO FDSys XML | Text
      DEPARTMENT OF LABOR, Occupational Safety and Health Administration
      Final rule.
      The final rule becomes effective on July 10, 2014. (Certain provisions have compliance deadlines after this date as explained later in this preamble.)
      29 CFR Parts 1910 and 1926

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code

Title 29 published on 2013-07-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 29 CFR 1926 after this date.

  • 2014-04-15; vol. 79 # 72 - Tuesday, April 15, 2014
    1. 79 FR 21164 - Cranes and Derricks in Construction: Operator Certification
      GPO FDSys XML | Text
      DEPARTMENT OF LABOR, Occupational Safety and Health Administration
      Notice of informal public hearing.
      Informal public hearing: The informal public hearing will be held on Monday, May 19, 2014, at 9:30 a.m. in the auditorium of the U.S. Department of Labor, 200 Constitution Avenue NW., Washington, DC 20210. Notice of intention to appear: Each person who wishes to testify at the hearing must submit a notice of intention to appear by April 25, 2014. Each person who files a notice of intention to appear may submit a written copy of additional comments to the record before or during the hearing for inclusion in the hearing record. Organizations may submit a single notice of intention to appear regarding multiple members of that organization, but the notice must list the name, occupational title, and position of each individual who plans to testify. In addition, all notices must also include the following information: (1) An email address or other contact information for receiving additional information about the hearing; (2) Name of the establishment or organization, if any, that each individual represents; (3) A brief summary of any documentary evidence each individual plans to present.
      29 CFR Part 1926