29 CFR 1926.1402 - Ground conditions.

Status message

There are 3 Updates appearing in the Federal Register for 29 CFR 1926. View below or at eCFR (GPOAccess)
§ 1926.1402 Ground conditions.
(a) Definitions.
(1) “Ground conditions” means the ability of the ground to support the equipment (including slope, compaction, and firmness).
(2) “Supporting materials” means blocking, mats, cribbing, marsh buggies (in marshes/wetlands), or similar supporting materials or devices.
(b) The equipment must not be assembled or used unless ground conditions are firm, drained, and graded to a sufficient extent so that, in conjunction (if necessary) with the use of supporting materials, the equipment manufacturer's specifications for adequate support and degree of level of the equipment are met. The requirement for the ground to be drained does not apply to marshes/wetlands.
(c) The controlling entity must:
(1) Ensure that ground preparations necessary to meet the requirements in paragraph (b) of this section are provided.
(2) Inform the user of the equipment and the operator of the location of hazards beneath the equipment set-up area (such as voids, tanks, utilities) if those hazards are identified in documents (such as site drawings, as-built drawings, and soil analyses) that are in the possession of the controlling entity (whether at the site or off-site) or the hazards are otherwise known to that controlling entity.
(d) If there is no controlling entity for the project, the requirement in paragraph (c)(1) of this section must be met by the employer that has authority at the site to make or arrange for ground preparations needed to meet paragraph (b) of this section.
(e) If the A/D director or the operator determines that ground conditions do not meet the requirements in paragraph (b) of this section, that person's employer must have a discussion with the controlling entity regarding the ground preparations that are needed so that, with the use of suitable supporting materials/devices (if necessary), the requirements in paragraph (b) of this section can be met.
(f) This section does not apply to cranes designed for use on railroad tracks when used on railroad tracks that are part of the general railroad system of transportation that is regulated pursuant to the Federal Railroad Administration under 49 CFR part 213 and that comply with applicable Federal Railroad Administration requirements.

Title 29 published on 2013-07-01

The following are only the Rules published in the Federal Register after the published date of Title 29.

For a complete list of all Rules, Proposed Rules, and Notices view the Rulemaking tab.

  • 2014-04-11; vol. 79 # 70 - Friday, April 11, 2014
    1. 79 FR 20316 - Electric Power Generation, Transmission, and Distribution; Electrical Protective Equipment
      GPO FDSys XML | Text
      DEPARTMENT OF LABOR, Occupational Safety and Health Administration
      Final rule.
      The final rule becomes effective on July 10, 2014. (Certain provisions have compliance deadlines after this date as explained later in this preamble.)
      29 CFR Parts 1910 and 1926

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code

Title 29 published on 2013-07-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 29 CFR 1926 after this date.

  • 2014-04-15; vol. 79 # 72 - Tuesday, April 15, 2014
    1. 79 FR 21164 - Cranes and Derricks in Construction: Operator Certification
      GPO FDSys XML | Text
      DEPARTMENT OF LABOR, Occupational Safety and Health Administration
      Notice of informal public hearing.
      Informal public hearing: The informal public hearing will be held on Monday, May 19, 2014, at 9:30 a.m. in the auditorium of the U.S. Department of Labor, 200 Constitution Avenue NW., Washington, DC 20210. Notice of intention to appear: Each person who wishes to testify at the hearing must submit a notice of intention to appear by April 25, 2014. Each person who files a notice of intention to appear may submit a written copy of additional comments to the record before or during the hearing for inclusion in the hearing record. Organizations may submit a single notice of intention to appear regarding multiple members of that organization, but the notice must list the name, occupational title, and position of each individual who plans to testify. In addition, all notices must also include the following information: (1) An email address or other contact information for receiving additional information about the hearing; (2) Name of the establishment or organization, if any, that each individual represents; (3) A brief summary of any documentary evidence each individual plans to present.
      29 CFR Part 1926