§ 1926.1419 Signals—general requirements.
(a) A signal person must be provided in each of the following situations:
(1) The point of operation, meaning the load travel or the area near or at load placement, is not in full view of the operator.
(2) When the equipment is traveling, the view in the direction of travel is obstructed.
(3) Due to site specific safety concerns, either the operator or the person handling the load determines that it is necessary.
(b) Types of signals. Signals to operators must be by hand, voice, audible, or new signals.
(c) Hand signals.
(1) When using hand signals, the Standard Method must be used (see appendix A of this subpart). Exception: Where use of the Standard Method for hand signals is infeasible, or where an operation or use of an attachment is not covered in the Standard Method, non-standard hand signals may be used in accordance with paragraph (c)(2) of this section.
(2) Non-standard hand signals. When using non-standard hand signals, the signal person, operator, and lift director (where there is one) must contact each other prior to the operation and agree on the non-standard hand signals that will be used.
(d) New signals. Signals other than hand, voice, or audible signals may be used where the employer demonstrates that:
(1) The new signals provide at least equally effective communication as voice, audible, or Standard Method hand signals, or
(2) The new signals comply with a national consensus standard that provides at least equally effective communication as voice, audible, or Standard Method hand signals.
(e) Suitability. The signals used (hand, voice, audible, or new), and means of transmitting the signals to the operator (such as direct line of sight, video, radio, etc.), must be appropriate for the site conditions.
(f) During operations requiring signals, the ability to transmit signals between the operator and signal person must be maintained. If that ability is interrupted at any time, the operator must safely stop operations requiring signals until it is reestablished and a proper signal is given and understood.
(g) If the operator becomes aware of a safety problem and needs to communicate with the signal person, the operator must safely stop operations. Operations must not resume until the operator and signal person agree that the problem has been resolved.
(h) Only one person may give signals to a crane/derrick at a time, except in circumstances covered by paragraph (j) of this section.
(i) [Reserved]
(j) Anyone who becomes aware of a safety problem must alert the operator or signal person by giving the stop or emergency stop signal. (Note:§ 1926.1417(y) requires the operator to obey a stop or emergency stop signal).
(k) All directions given to the operator by the signal person must be given from the operator's direction perspective.
(l) [Reserved]
(m) Communication with multiple cranes/derricks. Where a signal person(s) is in communication with more than one crane/derrick, a system must be used for identifying the crane/derrick each signal is for, as follows:
(1) for each signal, prior to giving the function/direction, the signal person must identify the crane/derrick the signal is for, or
(2) must use an equally effective method of identifying which crane/derrick the signal is for.

Title 29 published on 2013-07-01

The following are only the Rules published in the Federal Register after the published date of Title 29.

For a complete list of all Rules, Proposed Rules, and Notices view the Rulemaking tab.

  • 2014-09-26; vol. 79 # 187 - Friday, September 26, 2014
    1. 79 FR 57785 - Cranes and Derricks in Construction: Operator Certification
      GPO FDSys XML | Text
      DEPARTMENT OF LABOR, Occupational Safety and Health Administration
      Final rule.
      This final rule will become effective November 9, 2014.
      29 CFR Part 1926

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code

Title 29 published on 2013-07-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 29 CFR 1926 after this date.

  • 2014-10-10; vol. 79 # 197 - Friday, October 10, 2014
    1. 79 FR 61384 - Chemical Management and Permissible Exposure Limits (PELs)
      GPO FDSys XML | Text
      DEPARTMENT OF LABOR, Occupational Safety and Health Administration
      Request for Information (RFI).
      Comments must be submitted by the following dates: Hard copy: must be submitted (postmarked or sent) by April 8, 2015. Electronic transmission or facsimile: must be submitted by April 8, 2015.
      29 CFR Parts 1910, 1915, 1917, 1918, and 1926