§ 1926.956 Underground lines.
(a) Guarding and ventilating street opening used for access to underground lines or equipment.
(1) Appropriate warning signs shall be promptly placed when covers of manholes, handholes, or vaults are removed. What is an appropriate warning sign is dependent upon the nature and location of the hazards involved.
(2) Before an employee enters a street opening, such as a manhole or an unvented vault, it shall be promptly protected with a barrier, temporary cover, or other suitable guard.
(3) When work is to be performed in a manhole or unvented vault:
(i) No entry shall be permitted unless forced ventilation is provided or the atmosphere is found to be safe by testing for oxygen deficiency and the presence of explosive gases or fumes;
(ii) Where unsafe conditions are detected, by testing or other means, the work area shall be ventilated and otherwise made safe before entry;
(iii) Provisions shall be made for an adequate continuous supply of air.
(b) Work in manholes.
(1) While work is being performed in manholes, an employee shall be available in the immediate vicinity to render emergency assistance as may be required. This shall not preclude the employee in the immediate vicinity from occasionally entering a manhole to provide assistance, other than emergency. This requirement does not preclude a qualified employee, working alone, from entering for brief periods of time, a manhole where energized cables or equipment are in service, for the purpose of inspection, housekeeping, taking readings, or similar work if such work can be performed safely.
(2) When open flames must be used or smoking is permitted in manholes, extra precautions shall be taken to provide adequate ventilation.
(3) Before using open flames in a manhole or excavation in an area where combustible gases or liquids may be present, such as near a gasoline service station, the atmosphere of the manhole or excavation shall be tested and found safe or cleared of the combustible gases or liquids.
(c) Trenching and excavating.
(1) During excavation or trenching, in order to prevent the exposure of employees to the hazards created by damage to dangerous underground facilities, efforts shall be made to determine the location of such facilities and work conducted in a manner designed to avoid damage.
(2) Trenching and excavation operations shall comply with §§ 1926.651 and 1926.652.
(3) When underground facilities are exposed (electric, gas, water, telephone, etc.) they shall be protected as necessary to avoid damage.
(4) Where multiple cables exist in an excavation, cables other than the one being worked on shall be protected as necessary.
(5) When multiple cables exist in an excavation, the cable to be worked on shall be identified by electrical means unless its identity is obvious by reason of distinctive appearance.
(6) Before cutting into a cable or opening a splice, the cable shall be identified and verified to be the proper cable.
(7) When working on buried cable or on cable in manholes, metallic sheath continuity shall be maintained by bonding across the opening or by equivalent means.

Title 29 published on 2013-07-01

The following are only the Rules published in the Federal Register after the published date of Title 29.

For a complete list of all Rules, Proposed Rules, and Notices view the Rulemaking tab.

  • 2014-04-11; vol. 79 # 70 - Friday, April 11, 2014
    1. 79 FR 20316 - Electric Power Generation, Transmission, and Distribution; Electrical Protective Equipment
      GPO FDSys XML | Text
      DEPARTMENT OF LABOR, Occupational Safety and Health Administration
      Final rule.
      The final rule becomes effective on July 10, 2014. (Certain provisions have compliance deadlines after this date as explained later in this preamble.)
      29 CFR Parts 1910 and 1926

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code

Title 29 published on 2013-07-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 29 CFR 1926 after this date.

  • 2014-04-15; vol. 79 # 72 - Tuesday, April 15, 2014
    1. 79 FR 21164 - Cranes and Derricks in Construction: Operator Certification
      GPO FDSys XML | Text
      DEPARTMENT OF LABOR, Occupational Safety and Health Administration
      Notice of informal public hearing.
      Informal public hearing: The informal public hearing will be held on Monday, May 19, 2014, at 9:30 a.m. in the auditorium of the U.S. Department of Labor, 200 Constitution Avenue NW., Washington, DC 20210. Notice of intention to appear: Each person who wishes to testify at the hearing must submit a notice of intention to appear by April 25, 2014. Each person who files a notice of intention to appear may submit a written copy of additional comments to the record before or during the hearing for inclusion in the hearing record. Organizations may submit a single notice of intention to appear regarding multiple members of that organization, but the notice must list the name, occupational title, and position of each individual who plans to testify. In addition, all notices must also include the following information: (1) An email address or other contact information for receiving additional information about the hearing; (2) Name of the establishment or organization, if any, that each individual represents; (3) A brief summary of any documentary evidence each individual plans to present.
      29 CFR Part 1926