30 CFR 250.1156 - What steps must I take to receive approval to produce within 500 feet of a unit or lease line?

Status message

There is 1 rule appearing in the Federal Register for 30 CFR 250. View below or at eCFR (GPOAccess)
prev | next
§ 250.1156 What steps must I take to receive approval to produce within 500 feet of a unit or lease line?
(a) You must obtain approval from the Regional Supervisor before you start producing from a reservoir within a well that has any portion of the completed interval less than 500 feet from a unit or lease line. Submit to BSEE the service fee listed in § 250.125, according to the instructions in § 250.126, and the supporting information, as listed in the table in § 250.1167, with your request. The Regional Supervisor will determine whether approval of your request will maximize ultimate recovery, avoid the waste of natural resources, or protect correlative rights. You do not need to obtain approval if the adjacent leases or units have the same unit, lease (record title and operating rights), and royalty interests as the lease or unit you plan to produce. You do not need to obtain approval if the adjacent block is unleased.
(b) You must notify the operator(s) of adjacent property(ies) that are within 500 feet of the completion, if the adjacent acreage is a leased block in the Federal OCS. You must provide the Regional Supervisor proof of the date of the notification. The operators of the adjacent properties have 30 days after receiving the notification to provide the Regional Supervisor letters of acceptance or objection. If an adjacent operator does not respond within 30 days, the Regional Supervisor will presume there are no objections and proceed with a decision. The notification must include:
(1) The well name;
(2) The rectangular coordinates (x, y) of the location of the top and bottom of the completion or target completion referenced to the North American Datum 1983, and the subsea depths of the top and bottom of the completion or target completion;
(3) The distance from the completion or target completion to the unit or lease line at its nearest point; and
(4) A statement indicating whether or not it will be a high-capacity completion having a perforated or open hole interval greater than 150 feet measured depth.

Title 30 published on 2013-07-01

The following are only the Rules published in the Federal Register after the published date of Title 30.

For a complete list of all Rules, Proposed Rules, and Notices view the Rulemaking tab.

  • 2013-10-01; vol. 78 # 190 - Tuesday, October 1, 2013
    1. 78 FR 60208 - Oil and Gas and Sulphur Operations in the Outer Continental Shelf—Adjustment of Service Fees
      GPO FDSys XML | Text
      DEPARTMENT OF THE INTERIOR, Bureau of Safety and Environmental Enforcement
      Final rule.
      This final rule becomes effective on October 1, 2013.
      30 CFR Part 250

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code
U.S. Code: Title 30 - MINERAL LANDS AND MINING
U.S. Code: Title 31 - MONEY AND FINANCE
U.S. Code: Title 43 - PUBLIC LANDS

Title 30 published on 2013-07-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 30 CFR 250 after this date.

  • 2013-10-01; vol. 78 # 190 - Tuesday, October 1, 2013
    1. 78 FR 60208 - Oil and Gas and Sulphur Operations in the Outer Continental Shelf—Adjustment of Service Fees
      GPO FDSys XML | Text
      DEPARTMENT OF THE INTERIOR, Bureau of Safety and Environmental Enforcement
      Final rule.
      This final rule becomes effective on October 1, 2013.
      30 CFR Part 250