When may I flare or vent gas?
(a) You must request and receive approval from the Regional Supervisor to flare or vent natural gas at your facility, except in the following situations:
Condition Additional requirements
(1) When the gas is lease use gas (produced natural gas which is used on or for the benefit of lease operations such as gas used to operate production facilities) or is used as an additive necessary to burn waste products, such as H2S The volume of gas flared or vented may not exceed the amount necessary for its intended purpose. Burning waste products may require approval under other regulations.
(2) During the restart of a facility that was shut in because of weather conditions, such as a hurricane Flaring or venting may not exceed 48 cumulative hours without Regional Supervisor approval.
(3) During the blow down of transportation pipelines downstream of the royalty meter (i) You must report the location, time, flare/vent volume, and reason for flaring/venting to the Regional Supervisor in writing within 72 hours after the incident is over.
(ii) Additional approval may be required under subparts H and J of this part.
(4) During the unloading or cleaning of a well, drill-stem testing, production testing, other well-evaluation testing, or the necessary blow down to perform these procedures You may not exceed 48 cumulative hours of flaring or venting per unloading or cleaning or testing operation on a single completion without Regional Supervisor approval.
(5) When properly working equipment yields flash gas (natural gas released from liquid hydrocarbons as a result of a decrease in pressure, an increase in temperature, or both) from storage vessels or other low-pressure production vessels, and you cannot economically recover this flash gas You may not flare or vent more than an average of 50 MCF per day during any calendar month without Regional Supervisor approval.
(6) When the equipment works properly but there is a temporary upset condition, such as a hydrate or paraffin plug (i) For oil-well gas and gas-well flash gas (natural gas released from condensate as a result of a decrease in pressure, an increase in temperature, or both), you may not exceed 48 continuous hours of flaring or venting without Regional Supervisor approval.
(ii) For primary gas-well gas (natural gas from a gas well completion that is at or near its wellhead pressure; this does not include flash gas), you may not exceed 2 continuous hours of flaring or venting without Regional Supervisor approval.
(iii) You may not exceed 144 cumulative hours of flaring or venting during a calendar month without Regional Supervisor approval.
(7) When equipment fails to work properly, during equipment maintenance and repair, or when you must relieve system pressures (i) For oil-well gas and gas-well flash gas, you may not exceed 48 continuous hours of flaring or venting without Regional Supervisor approval.
(ii) For primary gas-well gas, you may not exceed 2 continuous hours of flaring or venting without Regional Supervisor approval.
(iii) You may not exceed 144 cumulative hours of flaring or venting during a calendar month without Regional Supervisor approval.
(iv) The continuous and cumulative hours allowed under this paragraph may be counted separately from the hours under paragraph (a)(6) of this section.
(b) Regardless of the requirements in paragraph (a) of this section, you must not flare or vent gas over the volume approved in your Development Operations Coordination Document (DOCD) or your Development and Production Plan (DPP).
(c) The Regional Supervisor may establish alternative approval procedures to cover situations when you cannot contact the MMS office, such as during non-office hours.
(d) The Regional Supervisor may specify a volume limit, or a shorter time limit than specified elsewhere in this part, in order to prevent air quality degradation or loss of reserves.
(e) If you flare or vent gas without the required approval, or if the Regional Supervisor determines that you were negligent or could have avoided flaring or venting the gas, the hydrocarbons will be considered avoidably lost or wasted. You must pay royalties on the loss or waste, according to part 202 of this title. You must value any gas or liquid hydrocarbons avoidably lost or wasted under the provisions of part 206 of this title.
(f) Fugitive emissions from valves, fittings, flanges, pressure relief valves or similar components do not require approval under this subpart unless specifically required by the Regional Supervisor.

Title 30 published on 2012-07-01

The following are only the Rules published in the Federal Register after the published date of Title 30.

For a complete list of all Rules, Proposed Rules, and Notices view the Rulemaking tab.

  • 2013-04-05; vol. 78 # 66 - Friday, April 5, 2013
    1. 78 FR 20423 - Oil and Gas and Sulphur Operations in the Outer Continental Shelf—Revisions to Safety and Environmental Management Systems
      GPO FDSys XML | Text
      DEPARTMENT OF THE INTERIOR, Bureau of Safety and Environmental Enforcement
      Final rule.
      This rule becomes effective on June 4, 2013. You must comply with the provisions of this rule on or before June 4, 2014, except the auditing requirements under § 250.1920. You must be in compliance with § 250.1920 by June 5, 2015. The incorporation by reference of certain publications listed in the rule is approved by the Director of the Federal Register as of June 4, 2013.
      30 CFR Part 250

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code
USC : Title 31 - MONEY AND FINANCE

§ 9701 - Fees and charges for Government services and things of value

USC : Title 43 - PUBLIC LANDS

§ 1331 - Definitions

§ 1332 - Congressional declaration of policy

§ 1333 - Laws and regulations governing lands

§ 1334 - Administration of leasing

§ 1335 - Validation and maintenance of prior leases

§ 1336 - Controversies over jurisdiction; agreements; payments; final settlement or adjudication; approval of notice concerning oil and gas operations in Gulf of Mexico

§ 1337 - Leases, easements, and rights-of-way on the outer Continental Shelf

§ 1338 - Disposition of revenues

§ 1338a - Moneys received as a result of forfeiture by Outer Continental Shelf permittee, lessee, or right-of-way holder; return of excess amounts

§ 1339 - Repealed.

§ 1340 - Geological and geophysical explorations

§ 1341 - Reservation of lands and rights

§ 1342 - Prior claims as unaffected

§ 1343 - Repealed.

§ 1344 - Outer Continental Shelf leasing program

§ 1345 - Coordination and consultation with affected State and local governments

§ 1346 - Environmental studies

§ 1347 - Safety and health regulations

§ 1348 - Enforcement of safety and environmental regulations

§ 1349 - Citizens suits, jurisdiction and judicial review

§ 1350 - Remedies and penalties

§ 1351 - Oil and gas development and production

§ 1352 - Oil and gas information program

§ 1353 - Federal purchase and disposition of oil and gas

§ 1354 - Limitations on export of oil or gas

§ 1355 - Restrictions on employment of former officers or employees of Department of the Interior

§ 1356 - Documentary, registry and manning requirements

§ 1356a - Coastal impact assistance program

USC : Title 44 - PUBLIC PRINTING AND DOCUMENTS

§ 3501 - Purposes

§ 3502 - Definitions

§ 3503 - Office of Information and Regulatory Affairs

§ 3504 - Authority and functions of Director

§ 3505 - Assignment of tasks and deadlines

§ 3506 - Federal agency responsibilities

§ 3507 - Public information collection activities; submission to Director; approval and delegation

§ 3508 - Determination of necessity for information; hearing

§ 3509 - Designation of central collection agency

§ 3510 - Cooperation of agencies in making information available

§ 3511 - Establishment and operation of Government Information Locator Service

§ 3512 - Public protection

§ 3513 - Director review of agency activities; reporting; agency response

§ 3514 - Responsiveness to Congress

§ 3515 - Administrative powers

§ 3516 - Rules and regulations

§ 3517 - Consultation with other agencies and the public

§ 3518 - Effect on existing laws and regulations

§ 3519 - Access to information

§ 3520 - Establishment of task force on information collection and dissemination

§ 3521 - Authorization of appropriations

Title 30 published on 2012-07-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 30 CFR 250 after this date.

  • 2013-04-05; vol. 78 # 66 - Friday, April 5, 2013
    1. 78 FR 20423 - Oil and Gas and Sulphur Operations in the Outer Continental Shelf—Revisions to Safety and Environmental Management Systems
      GPO FDSys XML | Text
      DEPARTMENT OF THE INTERIOR, Bureau of Safety and Environmental Enforcement
      Final rule.
      This rule becomes effective on June 4, 2013. You must comply with the provisions of this rule on or before June 4, 2014, except the auditing requirements under § 250.1920. You must be in compliance with § 250.1920 by June 5, 2015. The incorporation by reference of certain publications listed in the rule is approved by the Director of the Federal Register as of June 4, 2013.
      30 CFR Part 250