§ 250.241 What must the DPP or DOCD include?
Your DPP or DOCD must include the following:
(a) Description, objectives, and schedule. A description, discussion of the objectives, and tentative schedule (from start to completion) of the development and production activities you propose to undertake. Examples of development and production activities include:
(1) Development drilling;
(2) Well test flaring;
(3) Installation of production platforms, satellite structures, subsea wellheads and manifolds, and lease term pipelines (see definition at § 250.105); and
(4) Installation of production facilities and conduct of production operations.
(b) Location. The location and water depth of each of your proposed wells and production facilities. Include a map showing the surface and bottom-hole location and water depth of each proposed well, the surface location of each production facility, and the locations of all associated drilling unit and construction barge anchors.
(c) Drilling unit. A description of the drilling unit and associated equipment you will use to conduct your proposed development drilling activities. Include a brief description of its important safety and pollution prevention features, and a table indicating the type and the estimated maximum quantity of fuels and oil that will be stored on the facility (see third definition of “facility” under § 250.105).
(d) Production facilities. A description of the production platforms, satellite structures, subsea wellheads and manifolds, lease term pipelines (see definition at § 250.105), production facilities, umbilicals, and other facilities you will use to conduct your proposed development and production activities. Include a brief description of their important safety and pollution prevention features, and a table indicating the type and the estimated maximum quantity of fuels and oil that will be stored on the facility (see third definition of “facility” under § 250.105).
(e) Service fee. You must include payment of the service fee listed in § 250.125.
[70 FR 51501, Aug. 30, 2005, as amended at 71 FR 40911, July 19, 2006]

Title 30 published on 2013-07-01

The following are only the Rules published in the Federal Register after the published date of Title 30.

For a complete list of all Rules, Proposed Rules, and Notices view the Rulemaking tab.

  • 2013-10-01; vol. 78 # 190 - Tuesday, October 1, 2013
    1. 78 FR 60208 - Oil and Gas and Sulphur Operations in the Outer Continental Shelf—Adjustment of Service Fees
      GPO FDSys XML | Text
      DEPARTMENT OF THE INTERIOR, Bureau of Safety and Environmental Enforcement
      Final rule.
      This final rule becomes effective on October 1, 2013.
      30 CFR Part 250

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code
U.S. Code: Title 30 - MINERAL LANDS AND MINING
U.S. Code: Title 31 - MONEY AND FINANCE
U.S. Code: Title 43 - PUBLIC LANDS

Title 30 published on 2013-07-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 30 CFR 250 after this date.

  • 2013-10-01; vol. 78 # 190 - Tuesday, October 1, 2013
    1. 78 FR 60208 - Oil and Gas and Sulphur Operations in the Outer Continental Shelf—Adjustment of Service Fees
      GPO FDSys XML | Text
      DEPARTMENT OF THE INTERIOR, Bureau of Safety and Environmental Enforcement
      Final rule.
      This final rule becomes effective on October 1, 2013.
      30 CFR Part 250