30 CFR 250.290 - What operations require approval of the Conceptual Plan?

§ 250.290 What operations require approval of the Conceptual Plan?
You may not complete any production well or install the subsea wellhead and well safety control system (often called the tree) before BSEE has approved the Conceptual Plan.

Title 30 published on 2014-07-01

no entries appear in the Federal Register after this date.

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code
U.S. Code: Title 30 - MINERAL LANDS AND MINING
U.S. Code: Title 31 - MONEY AND FINANCE
U.S. Code: Title 43 - PUBLIC LANDS