30 CFR 250.516 - Blowout preventer system tests, inspections, and maintenance.

There are 2 Updates appearing in the Federal Register for 30 CFR 250. Select the tab below to view, or View eCFR (GPOAccess)
§ 250.516
Blowout preventer system tests, inspections, and maintenance.
(a) BOP pressure testing timeframes. You must pressure test your BOP system:
(1) When installed; and
(2) Before 14 days have elapsed since your last BOP pressure test. You must begin to test your BOP system before 12 a.m. (midnight) on the 14th day following the conclusion of the previous test. However, the District Manager may require testing every 7 days if conditions or BOP performance warrant.
(b) BOP test pressures. When you test the BOP system, you must conduct a low pressure and a high pressure test for each BOP component. Each individual pressure test must hold pressure long enough to demonstrate that the tested component(s) holds the required pressure. The District Manager may approve or require other test pressures or practices. Required test pressures are as follows:
(1) All low pressure tests must be between 200 and 300 psi. Any initial pressure above 300 psi must be bled back to a pressure between 200 and 300 psi before starting the test. If the initial pressure exceeds 500 psi, you must bleed back to zero and reinitiate the test. You must conduct the low pressure test before the high pressure test.
(2) For ram-type BOP's, choke manifold, and other BOP equipment, the high pressure test must equal the rated working pressure of the equipment.
(3) For annular-type BOP's, the high pressure test must equal 70 percent of the rated working pressure of the equipment.
(c) Duration of pressure test. Each test must hold the required pressure for 5 minutes.
(1) For surface BOP systems and surface equipment of a subsea BOP system, a 3-minute test duration is acceptable if you record your test pressures on the outermost half of a 4-hour chart, on a 1-hour chart, or on a digital recorder.
(2) If the equipment does not hold the required pressure during a test, you must remedy the problem and retest the affected component(s).
(d) Additional BOP testing requirements. You must:
(1) Use water to test the surface BOP system;
(2) Stump test a subsurface BOP system before installation. You must use water to stump test a subsea BOP system. You may use drilling or completion fluids to conduct subsequent tests of a subsea BOP system;
(3) Alternate tests between control stations and pods. If a control station or pod is not functional, you must suspend further completion operations until that station or pod is operable;
(4) Pressure test the blind or blind-shear ram at least every 30 days;
(5) Function test annulars and rams every 7 days;
(6) Pressure-test variable bore-pipe rams against all sizes of pipe in use, excluding drill collars and bottom-hole tools;
(7) Test affected BOP components following the disconnection or repair of any well-pressure containment seal in the wellhead or BOP stack assembly;
(8) Test all ROV intervention functions on your subsea BOP stack during the stump test. You must also test at least one set of rams during the initial test on the seafloor. You must submit test procedures with your APM for District Manager approval. You must:
(i) Ensure that the ROV hot stabs are function tested and are capable of actuating, at a minimum, one set of pipe rams and one set of blind-shear rams and unlatching the LMRP;
(ii) Document all your test results and make them available to BOEMRE upon request; and
(9) Function test autoshear and deadman systems on your subsea BOP stack during the stump test. You must also test the deadman system during the initial test on the seafloor.
(i) You must submit test procedures with your APM for District Manager approval.
(ii) You must document all your test results and make them available to BOEMRE upon request.
(e) Postponing BOP tests. You may postpone a BOP test if you have well-control problems. You must conduct the required BOP test as soon as possible (i.e., first trip out of the hole) after the problem has been remedied. You must record the reason for postponing any test in the driller's report.
(f) Weekly crew drills. You must conduct a weekly drill to familiarize all personnel engaged in well-completion operations with appropriate safety measures.
(g) BOP inspections. (1) You must inspect your BOP system to ensure that the equipment functions properly. The BOP inspections must meet or exceed the provisions of Sections 17.10 and 18.10, Inspections, described in API RP 53, Recommended Practices for Blowout Prevention Equipment Systems for Drilling Wells (incorporated by reference as specified in § 250.198 ). You must document the procedures used, record the results, and make them available to BOEMRE upon request. You must maintain your records on the rig for 2 years or from the date of your last major inspection, whichever is longer.
(2) You must visually inspect your BOP system and marine riser at least once each day if weather and sea conditions permit. You may use television cameras to inspect this equipment. The District Manager may approve alternate methods and frequencies to inspect a marine riser.
(h) BOP maintenance. You must maintain your BOP system to ensure that the equipment functions properly. The BOP maintenance must meet or exceed the provisions of Sections 17.11 and 18.11, Maintenance; and Sections 17.12 and 18.12, Quality Management, described in API RP 53, Recommended Practices for Blowout Prevention Equipment Systems for Drilling Wells (incorporated by reference as specified in § 250.198 ). You must document the procedures used, record the results, and make available to BOEMRE upon request. You must maintain your records on the rig for 2 years or from the date of your last major inspection, whichever is longer.
(i) BOP test records. You must record the time, date, and results of all pressure tests, actuations, crew drills, and inspections of the BOP system, system components, and marine riser in the driller's report. In addition, you must:
(1) Record BOP test pressures on pressure charts;
(2) Have your onsite representative certify (sign and date) BOP test charts and reports as correct;
(3) Document the sequential order of BOP and auxiliary equipment testing and the pressure and duration of each test. You may reference a BOP test plan if it is available at the facility;
(4) Identify the control station or pod used during the test;
(5) Identify any problems or irregularities observed during BOP system and equipment testing and record actions taken to remedy the problems or irregularities;
(6) Retain all records including pressure charts, driller's report, and referenced documents pertaining to BOP tests, actuations, and inspections at the facility for the duration of the completion activity; and
(7) After completion of the well, you must retain all the records listed in paragraph (i)(6) of this section for a period of 2 years at the facility, at the lessee's field office nearest the OCS facility, or at another location conveniently available to the District Manager.
(j) Alternate methods. The District Manager may require, or approve, more frequent testing, as well as different test pressures and inspection methods, or other practices.
[63 FR 29607, June 1, 1998, as amended at 75 FR 63375, Oct. 14, 2010]

Title 30 published on 2012-07-01

The following are only the Rules published in the Federal Register after the published date of Title 30.

For a complete list of all Rules, Proposed Rules, and Notices view the Rulemaking tab.

  • 2013-04-05; vol. 78 # 66 - Friday, April 5, 2013
    1. 78 FR 20423 - Oil and Gas and Sulphur Operations in the Outer Continental Shelf—Revisions to Safety and Environmental Management Systems
      GPO FDSys XML | Text
      DEPARTMENT OF THE INTERIOR, Bureau of Safety and Environmental Enforcement
      Final rule.
      This rule becomes effective on June 4, 2013. You must comply with the provisions of this rule on or before June 4, 2014, except the auditing requirements under § 250.1920. You must be in compliance with § 250.1920 by June 5, 2015. The incorporation by reference of certain publications listed in the rule is approved by the Director of the Federal Register as of June 4, 2013.
      30 CFR Part 250

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code
USC : Title 31 - MONEY AND FINANCE

§ 9701 - Fees and charges for Government services and things of value

USC : Title 43 - PUBLIC LANDS

§ 1331 - Definitions

§ 1332 - Congressional declaration of policy

§ 1333 - Laws and regulations governing lands

§ 1334 - Administration of leasing

§ 1335 - Validation and maintenance of prior leases

§ 1336 - Controversies over jurisdiction; agreements; payments; final settlement or adjudication; approval of notice concerning oil and gas operations in Gulf of Mexico

§ 1337 - Leases, easements, and rights-of-way on the outer Continental Shelf

§ 1338 - Disposition of revenues

§ 1338a - Moneys received as a result of forfeiture by Outer Continental Shelf permittee, lessee, or right-of-way holder; return of excess amounts

§ 1339 - Repealed.

§ 1340 - Geological and geophysical explorations

§ 1341 - Reservation of lands and rights

§ 1342 - Prior claims as unaffected

§ 1343 - Repealed.

§ 1344 - Outer Continental Shelf leasing program

§ 1345 - Coordination and consultation with affected State and local governments

§ 1346 - Environmental studies

§ 1347 - Safety and health regulations

§ 1348 - Enforcement of safety and environmental regulations

§ 1349 - Citizens suits, jurisdiction and judicial review

§ 1350 - Remedies and penalties

§ 1351 - Oil and gas development and production

§ 1352 - Oil and gas information program

§ 1353 - Federal purchase and disposition of oil and gas

§ 1354 - Limitations on export of oil or gas

§ 1355 - Restrictions on employment of former officers or employees of Department of the Interior

§ 1356 - Documentary, registry and manning requirements

§ 1356a - Coastal impact assistance program

USC : Title 44 - PUBLIC PRINTING AND DOCUMENTS

§ 3501 - Purposes

§ 3502 - Definitions

§ 3503 - Office of Information and Regulatory Affairs

§ 3504 - Authority and functions of Director

§ 3505 - Assignment of tasks and deadlines

§ 3506 - Federal agency responsibilities

§ 3507 - Public information collection activities; submission to Director; approval and delegation

§ 3508 - Determination of necessity for information; hearing

§ 3509 - Designation of central collection agency

§ 3510 - Cooperation of agencies in making information available

§ 3511 - Establishment and operation of Government Information Locator Service

§ 3512 - Public protection

§ 3513 - Director review of agency activities; reporting; agency response

§ 3514 - Responsiveness to Congress

§ 3515 - Administrative powers

§ 3516 - Rules and regulations

§ 3517 - Consultation with other agencies and the public

§ 3518 - Effect on existing laws and regulations

§ 3519 - Access to information

§ 3520 - Establishment of task force on information collection and dissemination

§ 3521 - Authorization of appropriations

Title 30 published on 2012-07-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 30 CFR 250 after this date.

  • 2013-04-05; vol. 78 # 66 - Friday, April 5, 2013
    1. 78 FR 20423 - Oil and Gas and Sulphur Operations in the Outer Continental Shelf—Revisions to Safety and Environmental Management Systems
      GPO FDSys XML | Text
      DEPARTMENT OF THE INTERIOR, Bureau of Safety and Environmental Enforcement
      Final rule.
      This rule becomes effective on June 4, 2013. You must comply with the provisions of this rule on or before June 4, 2014, except the auditing requirements under § 250.1920. You must be in compliance with § 250.1920 by June 5, 2015. The incorporation by reference of certain publications listed in the rule is approved by the Director of the Federal Register as of June 4, 2013.
      30 CFR Part 250