30 CFR 800.14 - Determination of bond amount.

§ 800.14 Determination of bond amount.
(a) The amount of the bond required for each bonded area shall:
(1) Be determined by the regulatory authority;
(2) Depend upon the requirements of the approved permit and reclamation plan;
(3) Reflect the probable difficulty of reclamation, giving consideration to such factors as topography, geology, hydrology, and revegetation potential; and
(4) Be based on, but not limited to, the estimated cost submitted by the permit applicant.
(b) The amount of the bond shall be sufficient to assure the completion of the reclamation plan if the work has to be performed by the regulatory authority in the event of forfeiture, and in no case shall the total bond initially posted for the entire area under one permit be less than $10,000.
(c) An operator's financial responsibility under § 817.121(c) of this chapter for repairing material damage resulting from subsidence may be satisfied by the liability insurance policy required under § 800.60.

Title 30 published on 2014-07-01

no entries appear in the Federal Register after this date.

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code
U.S. Code: Title 30 - MINERAL LANDS AND MINING
Public Laws