30 CFR 817.113 - Revegetation: Timing.

§ 817.113 Revegetation: Timing.
Disturbed areas shall be planted during the first normal period for favorable planting conditions after replacement of the plant-growth medium. The normal period for favorable planting is that planting time generally accepted locally for the type of plant materials selected.
[48 FR 40161, Sept. 2, 1983]

Title 30 published on 2014-07-01

no entries appear in the Federal Register after this date.

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code
U.S. Code: Title 30 - MINERAL LANDS AND MINING

Title 30 published on 2014-07-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 30 CFR 817 after this date.

  • 2014-08-25; vol. 79 # 164 - Monday, August 25, 2014
    1. 79 FR 50565 - Petition To Initiate Rulemaking; Use of Explosives on Surface Coal Mining Operations
      GPO FDSys XML | Text
      DEPARTMENT OF THE INTERIOR, Office of Surface Mining Reclamation and Enforcement
      Notice of availability of petition to initiate rulemaking; extension of comment period.
      The comment period for the petition for rulemaking published on July 25, 2014 (79 FR 43326), is extended. We will review and consider all comments submitted to the addresses listed below (see ADDRESSES ) on or before September 25, 2014.
      30 CFR Parts 816 and 817