40 CFR 147.2921 - Schedule of compliance.

§ 147.2921 Schedule of compliance.
The permit may, when appropriate, specify a schedule of compliance leading to compliance with the Safe Drinking Water Act and the Osage UIC regulations.
(a) Any schedule of compliance shall require compliance as soon as possible, and in no case later than three years after the effective date of the permit.
(b) If a permit establishes a schedule of compliance which exceeds one year from the date of permit issuance, the schedule shall set forth interim requirements and the dates for their achievement.
(1) The time between interim dates shall not exceed one year.
(2) If the time necessary for completion of any interim requirement is more than 1 year and is not readily divisible into stages for completion, the permit shall specify interim dates for the submission of reports of progress toward completion of the interim requirements and indicate a projected completion date.
(c) The permit shall be written to require that if a schedule of compliance is applicable, progress reports be submitted no later than 30 days following each interim date and the final date of compliance.

Title 40 published on 2013-07-01

no entries appear in the Federal Register after this date.

Title 40 published on 2013-07-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 40 CFR 147 after this date.

  • 2013-08-09; vol. 78 # 154 - Friday, August 9, 2013
    1. 78 FR 48639 - North Dakota Underground Injection Control Program Revision Application
      GPO FDSys XML | Text
      ENVIRONMENTAL PROTECTION AGENCY
      Notice of public comment period and opportunity to request a public hearing.
      Comments will be accepted until September 9, 2013. Any member of the public can request a public hearing on this matter. A public hearing will only be held if requests indicate there is significant public interest. Request for a public hearing will be accepted until September 9, 2013. Requests for a public hearing may be mailed to: Craig Boomgaard EPA Region 8, 1595 Wynkoop Street, MSC 8P-W-UIC, Denver, Colorado, 80202. For additional information regarding the public hearing, please contact Craig Boomgaard (303) 312-6794 or boomgaard.craig@epa.gov.
      40 CFR Part 147