40 CFR 147.3006 - Injection pressure for existing Class II wells authorized by rule.

§ 147.3006 Injection pressure for existing Class II wells authorized by rule.
(a) Rule-authorized Class II saltwater disposal wells. In addition to the requirements of § 144.28(f)(3)(ii) of this chapter, the owner or operator shall, except during well stimulation, use an injection pressure measured at the wellhead that is not greater than the pressure calculated by using the following formula:
Pm=0.2d
where:
Pm=injection pressure at the wellhead in pounds per square inch
d=depth in feet to the top of the injection zone.
Owners and operators shall comply with this requirement no later than one year after the effective date of this program.
(b) Rule-authorized Class II enhanced recovery and hydrocarbon storage wells.
(1) In addition to the requirements of § 144.28(f)(3)(ii) of this chapter, owners and operators shall use an injection pressure no greater than the pressure established by the Director for the field or formation in which the well is located. The Director shall establish such maximum pressure after notice (including notice to the affected Tribe), opportunity for comment, and opportunity for public hearing according to the provisions of part 124, subpart A, of this chapter, and shall inform owners and operators and the affected Tribe in writing of the applicable maximum pressure; or
(2) An owner or operator may inject at a pressure greater than that specified in paragraph (b)(1) of this section for the field or formation in which he is operating after demonstrating in writing to the satisfaction of the Director that such injection pressure will not violate the requirements of § 144.28(f)(3)(ii) of this chapter. The Director may grant such a request after notice (including notice to the affected Tribe), opportunity for comment and opportunity for a public hearing according to the provisions of part 124, subpart A of this chapter.
(3) Prior to the time that the Director establishes rules for maximum injection pressure under paragraph (b)(1) of this section the owner or operator shall:
(i) Limit injection pressure to a value which will not exceed the operating requirements of § 144.28(f)(3)(ii); and
(ii) Submit data acceptable to the Director which defines the fracture pressure of the formation in which injection is taking place. A single submission may be made on behalf of two or more operators conducting operations in the same field and formation, if the Director approves. The data shall be submitted to the Director within one year of the effective date of this program.

Title 40 published on 2013-07-01

no entries appear in the Federal Register after this date.

Title 40 published on 2013-07-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 40 CFR 147 after this date.

  • 2013-08-09; vol. 78 # 154 - Friday, August 9, 2013
    1. 78 FR 48639 - North Dakota Underground Injection Control Program Revision Application
      GPO FDSys XML | Text
      ENVIRONMENTAL PROTECTION AGENCY
      Notice of public comment period and opportunity to request a public hearing.
      Comments will be accepted until September 9, 2013. Any member of the public can request a public hearing on this matter. A public hearing will only be held if requests indicate there is significant public interest. Request for a public hearing will be accepted until September 9, 2013. Requests for a public hearing may be mailed to: Craig Boomgaard EPA Region 8, 1595 Wynkoop Street, MSC 8P-W-UIC, Denver, Colorado, 80202. For additional information regarding the public hearing, please contact Craig Boomgaard (303) 312-6794 or boomgaard.craig@epa.gov.
      40 CFR Part 147