§ 265.197 Closure and post-closure care.
(a) At closure of a tank system, the owner or operator must remove or decontaminate all waste residues, contaminated containment system components (liners, etc.), contaminated soils, and structures and equipment contaminated with waste, and manage them as hazardous waste, unless § 261.3(d) of this Chapter applies. The closure plan, closure activities, cost estimates for closure, and financial responsibility for tank systems must meet all of the requirements specified in subparts G and H of this part.
(b) If the owner or operator demonstrates that not all contaminated soils can be practicably removed or decontaminated as required in paragraph (a) of this section, then the owner or operator must close the tank system and perform post-closure care in accordance with the closure and post-closure care requirements that apply to landfills (§ 265.310). In addition, for the purposes of closure, post-closure, and financial responsibility, such a tank system is then considered to be a landfill, and the owner or operator must meet all of the requirements for landfills specified in subparts G and H of this part.
(c) If an owner or operator has a tank system which does not have secondary containment that meets the requirements of § 265.193(b) through (f) and which is not exempt from the secondary containment requirements in accordance with § 265.193(g), then,
(1) The closure plan for the tank system must include both a plan for complying with paragraph (a) of this section and a contingent plan for complying with paragraph (b) of this section.
(2) A contingent post-closure plan for complying with paragraph (b) of this section must be prepared and submitted as part of the permit application.
(3) The cost estimates calculated for closure and post-closure care must reflect the costs of complying with the contingent closure plan and the contingent post-closure plan, if these costs are greater than the costs of complying with the closure plan prepared for the expected closure under paragraph (a) of this section.
(4) Financial assurance must be based on the cost estimates in paragraph (c)(3) of this section.
(5) For the purposes of the contingent closure and post-closure plans, such a tank system is considered to be a landfill, and the contingent plans must meet all of the closure, post-closure, and financial responsibility requirements for landfills under subparts G and H of this part.
[51 FR 25479, July 14, 1986, as amended at 71 FR 40275, July 14, 2006]

Title 40 published on 2013-07-01

The following are only the Rules published in the Federal Register after the published date of Title 40.

For a complete list of all Rules, Proposed Rules, and Notices view the Rulemaking tab.

  • 2014-02-07; vol. 79 # 26 - Friday, February 7, 2014
    1. 79 FR 7518 - Hazardous Waste Management System; Modification of the Hazardous Waste Manifest System; Electronic Manifests
      GPO FDSys XML | Text
      ENVIRONMENTAL PROTECTION AGENCY
      Final rule.
      This final rule is effective as a final agency action on August 6, 2014. However, the implementation and compliance date for these regulations will be delayed until such time as the e-Manifest system is shown to be ready for operation and the schedule of fees for manifest related services has been announced. EPA will publish a further document subsequent to this rule's effective date to announce the user fee schedule for manifest related activities. This document will also announce the date upon which compliance with this regulation will be required and upon which EPA will be ready to receive electronic manifests through the national e-Manifest system, in accordance with 40 CFR 3.2(a)(2).
      40 CFR Parts 260, 262, 263, 264, 265, and 271

Title 40 published on 2013-07-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 40 CFR 265 after this date.

  • 2014-02-07; vol. 79 # 26 - Friday, February 7, 2014
    1. 79 FR 7518 - Hazardous Waste Management System; Modification of the Hazardous Waste Manifest System; Electronic Manifests
      GPO FDSys XML | Text
      ENVIRONMENTAL PROTECTION AGENCY
      Final rule.
      This final rule is effective as a final agency action on August 6, 2014. However, the implementation and compliance date for these regulations will be delayed until such time as the e-Manifest system is shown to be ready for operation and the schedule of fees for manifest related services has been announced. EPA will publish a further document subsequent to this rule's effective date to announce the user fee schedule for manifest related activities. This document will also announce the date upon which compliance with this regulation will be required and upon which EPA will be ready to receive electronic manifests through the national e-Manifest system, in accordance with 40 CFR 3.2(a)(2).
      40 CFR Parts 260, 262, 263, 264, 265, and 271