40 CFR § 35.113 - Reimbursement for pre-award costs.

prev | next
§ 35.113 Reimbursement for pre-award costs.

(a) Notwithstanding the requirements of 2 CFR parts 200 and 1500, EPA may reimburse recipients for pre-award costs incurred from the beginning of the budget period established in the grant agreement if such costs would have been allowable if incurred after the award. Pre-award costs must be identified in the grant application EPA approves.

(b) The applicant incurs pre-award costs at its own risk. EPA is under no obligation to reimburse such costs unless they are included in an approved grant award.

[66 FR 1734, Jan. 9, 2001, as amended at 79 FR 76054, Dec. 19, 2014; 87 FR 30398, May 19, 2022]