40 CFR 49.10738 - Permits to construct.

Status message

There is 1 rule appearing in the Federal Register for 40 CFR 49. View below or at eCFR (GPOAccess)
§ 49.10738 Permits to construct.
Permits to construct are required for new major stationary sources and major modifications to existing major stationary sources pursuant to 40 CFR 52.21.

Title 40 published on 2013-07-01

The following are only the Rules published in the Federal Register after the published date of Title 40.

For a complete list of all Rules, Proposed Rules, and Notices view the Rulemaking tab.

  • 2013-10-02; vol. 78 # 191 - Wednesday, October 2, 2013
    1. 78 FR 60700 - Source Specific Federal Implementation Plan for Implementing Best Available Retrofit Technology for Four Corners Power Plant; Navajo Nation; Extension of Notification Deadline
      GPO FDSys XML | Text
      ENVIRONMENTAL PROTECTION AGENCY
      Final rule.
      This rule is effective on November 1, 2013.
      40 CFR Part 49

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code

Title 40 published on 2013-07-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 40 CFR 49 after this date.

  • 2014-05-02; vol. 79 # 85 - Friday, May 2, 2014
    1. 79 FR 25049 - Approval and Promulgation of Implementation Plans; Swinomish Indian Tribal Community; Tribal Implementation Plan
      GPO FDSys XML | Text
      ENVIRONMENTAL PROTECTION AGENCY
      Proposed rule.
      Comments must be received on or before June 2, 2014.
      40 CFR Part 49