§ 51.372 State Implementation Plan submissions.
(a) SIP submittals. The SIP shall address each of the elements covered in this subpart, including, but not limited to:
(1) A schedule of implementation of the program including interim milestones leading to mandatory testing. The milestones shall include, at a minimum:
(i) Passage of enabling statutory or other legal authority;
(ii) Proposal of draft regulations and promulgation of final regulations;
(iii) Issuance of final specifications and procedures;
(iv) Issuance of final Request for Proposals (if applicable);
(v) Licensing or certifications of stations and inspectors;
(vi) The date mandatory testing will begin for each model year to be covered by the program;
(vii) The date full-stringency cutpoints will take effect;
(viii) All other relevant dates;
(2) An analysis of emission level targets for the program using the most current EPA mobile source emission model or an alternative approved by the Administrator showing that the program meets the performance standard described in § 51.351 or § 51.352 of this subpart, as applicable;
(3) A description of the geographic coverage of the program, including ZIP codes if the program is not county-wide;
(4) A detailed discussion of each of the required design elements, including provisions for Federal facility compliance;
(5) Legal authority requiring or allowing implementation of the I/M program and providing either broad or specific authority to perform all required elements of the program;
(6) Legal authority for I/M program operation until such time as it is no longer necessary (i.e., until a Section 175 maintenance plan without an I/M program is approved by EPA);
(7) Implementing regulations, interagency agreements, and memoranda of understanding; and
(8) Evidence of adequate funding and resources to implement all aspects of the program.
(b) Submittal schedule. The SIP shall be submitted to EPA according to the following schedule—
(1) [Reserved]
(2) A SIP revision required as a result of designation for a National Ambient Air Quality Standard in place prior to implementation of the 8-hour ozone standard and including all necessary legal authority and the items specified in paragraphs (a)(1) through (a)(8) of this section, shall be submitted no later than November 15, 1993. For non-attainment areas designated and classified under the 8-hour ozone standard, a SIP revision including all necessary legal authority and the items specified in paragraphs (a)(1) through (a)(8) of this section, shall be submitted by May 8, 2007 or 1 year after the effective date of designation and classification under the 8-hour ozone National Ambient Air Quality Standard, whichever is later.
(3) [Reserved]
(c) Redesignation requests. Any nonattainment area that EPA determines would otherwise qualify for redesignation from nonattainment to attainment shall receive full approval of a State Implementation Plan (SIP) submittal under Sections 182(a)(2)(B) or 182(b)(4) if the submittal contains the following elements:
(1) Legal authority to implement a basic I/M program (or enhanced if the State chooses to opt up) as required by this subpart. The legislative authority for an I/M program shall allow the adoption of implementing regulations without requiring further legislation.
(2) A request to place the I/M plan (if no I/M program is currently in place or if an I/M program has been terminated,) or the I/M upgrade (if the existing I/M program is to continue without being upgraded) into the contingency measures portion of the maintenance plan upon redesignation.
(3) A contingency measure consisting of a commitment by the Governor or the Governor's designee to adopt or consider adopting regulations to implement an I/M program to correct a violation of the ozone or CO standard or other air quality problem, in accordance with the provisions of the maintenance plan.
(4) A contingency commitment that includes an enforceable schedule for adoption and implementation of the I/M program, and appropriate milestones. The schedule shall include the date for submission of a SIP meeting all of the requirements of this subpart. Schedule milestones shall be listed in months from the date EPA notifies the State that it is in violation of the ozone or CO standard or any earlier date specified in the State plan. Unless the State, in accordance with the provisions of the maintenance plan, chooses not to implement I/M, it must submit a SIP revision containing an I/M program no more than 18 months after notification by EPA.
(d) Basic areas continuing operation of I/M programs as part of their maintenance plan without implemented upgrades shall be assumed to be 80% as effective as an implemented, upgraded version of the same I/M program design, unless a State can demonstrate using operating information that the I/M program is more effective than the 80% level.
(e) SIP submittals to correct violations. SIP submissions required pursuant to a violation of the ambient ozone or CO standard (as discussed in paragraph (c) of this section) shall address all of the requirements of this subpart. The SIP shall demonstrate that performance standards in either § 51.351 or § 51.352 shall be met using an evaluation date (rounded to the nearest January for carbon monoxide and July for hydrocarbons) seven years after the date EPA notifies the State that it is in violation of the ozone or CO standard or any earlier date specified in the State plan. Emission standards for vehicles subject to an IM240 test may be phased in during the program but full standards must be in effect for at least one complete test cycle before the end of the 5-year period. All other requirements shall take effect within 24 months of the date EPA notifies the State that it is in violation of the ozone or CO standard or any earlier date specified in the State plan. The phase-in allowances of § 51.373(c) of this subpart shall not apply.
[57 FR 52987, Nov. 5, 1992, as amended at 60 FR 1738, Jan. 5, 1995; 60 FR 48036, Sept. 18, 1995; 61 FR 40946, Aug. 6, 1996; 61 FR 44119, Aug. 27, 1996; 71 FR 17711, Apr. 7, 2006]

Title 40 published on 2014-07-01

The following are only the Rules published in the Federal Register after the published date of Title 40.

For a complete list of all Rules, Proposed Rules, and Notices view the Rulemaking tab.

  • 2014-12-03; vol. 79 # 232 - Wednesday, December 3, 2014
    1. 79 FR 71663 - Rulemaking To Amend Dates in Federal Implementation Plans Addressing Interstate Transport of Ozone and Fine Particulate Matter
      GPO FDSys XML | Text
      ENVIRONMENTAL PROTECTION AGENCY
      Interim final rule with request for comment.
      This final rule is effective on December 3, 2014. The EPA will consider comments on this interim final rule received on or before February 2, 2015.
      40 CFR Parts 51, 52, and 97

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code
U.S. Code: Title 23 - HIGHWAYS
U.S. Code: Title 42 - THE PUBLIC HEALTH AND WELFARE

§ 7401 - Congressional findings and declaration of purpose

§ 7402 - Cooperative activities

§ 7403 - Research, investigation, training, and other activities

§ 7404 - Research relating to fuels and vehicles

§ 7405 - Grants for support of air pollution planning and control programs

§ 7406 - Interstate air quality agencies; program cost limitations

§ 7407 - Air quality control regions

§ 7408 - Air quality criteria and control techniques

§ 7409 - National primary and secondary ambient air quality standards

§ 7410 - State implementation plans for national primary and secondary ambient air quality standards

§ 7411 - Standards of performance for new stationary sources

§ 7412 - Hazardous air pollutants

§ 7413 - Federal enforcement

§ 7414 - Recordkeeping, inspections, monitoring, and entry

§ 7415 - International air pollution

§ 7416 - Retention of State authority

§ 7417 - Advisory committees

§ 7418 - Control of pollution from Federal facilities

§ 7419 - Primary nonferrous smelter orders

§ 7420 - Noncompliance penalty

§ 7421 - Consultation

§ 7422 - Listing of certain unregulated pollutants

§ 7423 - Stack heights

§ 7424 - Assurance of adequacy of State plans

§ 7425 - Measures to prevent economic disruption or unemployment

§ 7426 - Interstate pollution abatement

§ 7427 - Public notification

§ 7428 - State boards

§ 7429 - Solid waste combustion

§ 7430 - Emission factors

§ 7431 - Land use authority

§ 7450 to 7459 - Repealed.

§ 7470 - Congressional declaration of purpose

§ 7471 - Plan requirements

§ 7472 - Initial classifications

§ 7473 - Increments and ceilings

§ 7474 - Area redesignation

§ 7475 - Preconstruction requirements

§ 7476 - Other pollutants

§ 7477 - Enforcement

§ 7478 - Period before plan approval

§ 7479 - Definitions

§ 7491 - Visibility protection for Federal class I areas

§ 7492 - Visibility

§ 7501 - Definitions

§ 7502 - Nonattainment plan provisions in general

§ 7503 - Permit requirements

§ 7504 - Planning procedures

§ 7505 - Environmental Protection Agency grants

§ 7505a - Maintenance plans

§ 7506 - Limitations on certain Federal assistance

§ 7506a - Interstate transport commissions

§ 7507 - New motor vehicle emission standards in nonattainment areas

§ 7508 - Guidance documents

§ 7509 - Sanctions and consequences of failure to attain

§ 7509a - International border areas

§ 7511 - Classifications and attainment dates

§ 7511a - Plan submissions and requirements

§ 7511b - Federal ozone measures

§ 7511c - Control of interstate ozone air pollution

§ 7511d - Enforcement for Severe and Extreme ozone nonattainment areas for failure to attain

§ 7511e - Transitional areas

§ 7511f - NO

§ 7512 - Classification and attainment dates

§ 7512a - Plan submissions and requirements

§ 7513 - Classifications and attainment dates

§ 7513a - Plan provisions and schedules for plan submissions

§ 7513b - Issuance of RACM and BACM guidance

§ 7514 - Plan submission deadlines

§ 7514a - Attainment dates

§ 7515 - General savings clause

§ 7521 - Emission standards for new motor vehicles or new motor vehicle engines

§ 7522 - Prohibited acts

§ 7523 - Actions to restrain violations

§ 7524 - Civil penalties

§ 7525 - Motor vehicle and motor vehicle engine compliance testing and certification

§ 7541 - Compliance by vehicles and engines in actual use

§ 7542 - Information collection

§ 7543 - State standards

§ 7544 - State grants

§ 7545 - Regulation of fuels

§ 7546 - Renewable fuel

§ 7547 - Nonroad engines and vehicles

§ 7548 - Study of particulate emissions from motor vehicles

§ 7549 - High altitude performance adjustments

§ 7550 - Definitions

§ 7551 - Omitted

§ 7552 - Motor vehicle compliance program fees

§ 7553 - Prohibition on production of engines requiring leaded gasoline

§ 7554 - Urban bus standards

§ 7571 - Establishment of standards

§ 7572 - Enforcement of standards

§ 7573 - State standards and controls

§ 7574 - Definitions

§ 7581 - Definitions

§ 7582 - Requirements applicable to clean-fuel vehicles

§ 7583 - Standards for light-duty clean-fuel vehicles

§ 7584 - Administration and enforcement as per California standards

§ 7585 - Standards for heavy-duty clean-fuel vehicles (GVWR above 8,500 up to 26,000 lbs.)

§ 7586 - Centrally fueled fleets

§ 7587 - Vehicle conversions

§ 7588 - Federal agency fleets

§ 7589 - California pilot test program

§ 7590 - General provisions

§ 7601 - Administration

§ 7602 - Definitions

§ 7603 - Emergency powers

§ 7604 - Citizen suits

§ 7605 - Representation in litigation

§ 7606 - Federal procurement

§ 7607 - Administrative proceedings and judicial review

§ 7608 - Mandatory licensing

§ 7609 - Policy review

§ 7610 - Other authority

§ 7611 - Records and audit

§ 7612 - Economic impact analyses

§ 7613 - Repealed.

§ 7614 - Labor standards

§ 7615 - Separability

§ 7616 - Sewage treatment grants

§ 7617 - Economic impact assessment

§ 7618 - Repealed.

§ 7619 - Air quality monitoring

§ 7620 - Standardized air quality modeling

§ 7621 - Employment effects

§ 7622 - Employee protection

§ 7623 - Repealed.

§ 7624 - Cost of vapor recovery equipment

§ 7625 - Vapor recovery for small business marketers of petroleum products

42 U.S. Code § 7450 to 7459 - Repealed.

§ 7625a - Statutory construction

§ 7626 - Authorization of appropriations

§ 7627 - Air pollution from Outer Continental Shelf activities

§ 7628 - Demonstration grant program for local governments

§ 7641 - Noise abatement

§ 7642 - Authorization of appropriations

§ 7651 - Findings and purposes

§ 7651a - Definitions

§ 7651b - Sulfur dioxide allowance program for existing and new units

§ 7651c - Phase I sulfur dioxide requirements

§ 7651d - Phase II sulfur dioxide requirements

§ 7651e - Allowances for States with emissions rates at or below 0.80 lbs/mmBtu

§ 7651f - Nitrogen oxides emission reduction program

§ 7651g - Permits and compliance plans

§ 7651h - Repowered sources

§ 7651i - Election for additional sources

§ 7651j - Excess emissions penalty

§ 7651k - Monitoring, reporting, and recordkeeping requirements

42 U.S. Code § -

§ 7651m - Enforcement

§ 7651n - Clean coal technology regulatory incentives

42 U.S. Code § -

§ 7661 - Definitions

§ 7661a - Permit programs

§ 7661b - Permit applications

§ 7661c - Permit requirements and conditions

§ 7661d - Notification to Administrator and contiguous States

§ 7661e - Other authorities

§ 7661f - Small business stationary source technical and environmental compliance assistance program

§ 7671 - Definitions

§ 7671a - Listing of class I and class II substances

§ 7671b - Monitoring and reporting requirements

§ 7671c - Phase-out of production and consumption of class I substances

§ 7671d - Phase-out of production and consumption of class II substances

§ 7671e - Accelerated schedule

§ 7671f - Exchange authority

§ 7671g - National recycling and emission reduction program

§ 7671h - Servicing of motor vehicle air conditioners

§ 7671i - Nonessential products containing chlorofluorocarbons

§ 7671j - Labeling

§ 7671k - Safe alternatives policy

42 U.S. Code § -

§ 7671m - Relationship to other laws

§ 7671n - Authority of Administrator

42 U.S. Code § -

§ 7671p - International cooperation

§ 7671q - Miscellaneous provisions

Title 40 published on 2014-07-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 40 CFR 51 after this date.

  • 2014-12-03; vol. 79 # 232 - Wednesday, December 3, 2014
    1. 79 FR 71663 - Rulemaking To Amend Dates in Federal Implementation Plans Addressing Interstate Transport of Ozone and Fine Particulate Matter
      GPO FDSys XML | Text
      ENVIRONMENTAL PROTECTION AGENCY
      Interim final rule with request for comment.
      This final rule is effective on December 3, 2014. The EPA will consider comments on this interim final rule received on or before February 2, 2015.
      40 CFR Parts 51, 52, and 97